STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 302, section 1. The text section number identifies this passage in the reader.
Residual
Responsible
Rating
Proposed Controls
Initial
HOC
Risk
Risk
Activity Hazards
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Planning works Contact with overhead power EXTREME 5 Safe approach distances will be determined by plant operators and/or the Site Supervisor using the relevant state Site Management
around overhead lines legislation, COP and Australian Standards prior to any work commencing near overhead power lines. Contract Partner
powerlines Site Management
Contact with overhead power EXTREME 5 Consultation with the utility entity shall occur to inform of work activities when near assets and identify any specific
lines. controls that may be required. Contract Partner
Contact with covered / All work occurring near network assets must adhere to any requirements of an electricity entity responsible for the line.
underground services
Contact with overhead power EXTREME 5 No worker, equipment, loads being moved, crane or plant will be required to enter the exclusion zone around power Site Management
lines lines. Contract Partner
Contact with overhead power EXTREME 5 An electrical safety observer will work with the operator of any plant and equipment, which could enter the exclusion Site Management
lines zone. The electrical safety observer will have no other duty and will only observe one crane or piece of plant at a time. Contract Partner
Workers electrocuted / EXTREME 5 Work on site will be undertaken within the safe approach distances (i.e. exclusion zones) and special provisions will be Site Management
shocked made including: Contract Partner
- To notify and obtain written permission from the power authority before commencing work.
- Not to commence work until a pre-start site meeting, a risk assessment detailing the necessary controls to be
implemented and training has been completed.
Plan for working Striking underground services EXTREME Assessment of underground services completed prior to the commencement of works including: Site Management
around - DBYD
underground
power - Service location (i.e., scanning etc.)
- Potholing (positive identification of service location)
Planning for Inadvertent contact with EXTREME Assessment of live buildings to identify services remaining live during construction: Site Management
working around live electrical services Electrical contractor
If live permanent wiring is located where construction activity is occurring it, or its location shall be marked with the
electrical circuit words ‘LIVE WIRING’ at intervals not exceeding 5m.
Live permanent wiring shall be readily distinguishable from construction.
References AS/NZ 3012 Electrical Installations – Construction
AS/NZS 3000 Wiring
AS 3010 – Electrical installations – Generating sets
Review / Safety Interactions, Task Observations, SWMS Review Weekly HSE Inspection, Monthly Audit as per Procore Inspection Matrix
Monitoring
9.3Electrical equipment
Planning Electrocution HIGH 5 Contract Partner’s will supply an electrical register to demonstrate compliance with the above requirements Site Management
Contract Partner
Project Hazard/Risk Assessment / Page 60 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.