STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 318, section 1. The text section number identifies this passage in the reader.
Residual
Responsible
Rating
Initial
Proposed Controls
HOC
Risk
Risk
Activity Hazards
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Stressing of anchors Plant failure due to EXTREME 5 Stressing equipment has been calibrated as per Australian standards and any state regulator requirements. Site
inadequate servicing Management
and maintenance Contract Partner
12.3 Piling Activities
Planning Activity planning and EXTREME 5 All tasks involving the use of plant or equipment to have an approved SWMS with all workers trained in the Site
hazard identification approved work methods. Management
Contract Partner
Plant overturning EXTREME 5 Ensure the correct piling rig has been selected for the work Project Manager
Site Manager
Contract Partner
Plant overturning EXTREME 5 Set up area has been designed and approved by Geotechnical Engineer. To ensure the ground is suitable for Site
set up and machine will not become unstable or collapse. Working platform to be inspected after large rain Management
events. Contract Partner
Failure of piling rig EXTREME 5 All Contract Partner’s will provide a register for all equipment to be used on site. This register will detail Site
records of any tests, maintenance, inspections, commissioning, or alteration of the plant and must show Management
when the next service is due for each item. Contract Partner
Contact with EXTREME 5 Underground services, overhead power lines, unstable ground, and other excavations in the vicinity will be Site
overhead or identified and details given to the Contract Partner prior to setup and commencement of work. Management
underground Contract Partner
services
Failure to assess task EXTREME 5 0586–03 Excavation Permit to be issued prior to commencing piling works. Site
specific risks. Management
Contract Partner
Contact with
underground
services
Plant overturning. EXTREME 5 Initial Mobile Plant Checklist in Procore to be completed when a Piling Rig is brought onto site. The initial Site
plant prestart will be approved by Woollam site management, and a plant sticker will be placed on the Piling Management
Piling rig not Contract Partner
suitable for the Rig.
work
Use of piling rig Workers not EXTREME 5 Contract Partner’s will provide adequate supervision to ensure plant and equipment is used in accordance Site
suitably licenced or with manufacturer's instructions. Management
trained for the Contract Partner
activity.
Injury
Project Hazard/Risk Assessment / Page 76 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.