Total progress to date

Table 1: Total Progress to Date

  #     Deliverable                                                                             Progress
 1.1    1 Technical Advisory Group with TOR established                                         Achieved
 1.2    1 Project Manager appointed                                                             Achieved
 1.3    1 Project Implementation Plan completed and endorsed by Noosa Council                   Achieved
        1 Detailed Risk Assessment included
        1 Communications and Media Plan completed
        1 Monitoring, Evaluation and Reporting Plan completed
 1.4    3 community engagement forums facilitated                                               Achieved
        3 media statements released
 1.5    3 six monthly status updates submitted to Noosa Council                                 On Track
        3 annual reports submitted to Noosa Council
 2.1    1 Habitat suitability model developed which incorporates industry, Kabi Kabi and        Achieved
        public interests
 2.2    1 set of ‘all’ relevant state and local permits for oyster reef restoration obtained    Delayed
 2.3    1 set of engagement records provided to Noosa Council of public and stakeholder         Achieved
        consultations, including one-on-one meetings, open forums, media, etc.
 3.1    1 consultation completed                                                                Achieved
        1 volunteering opportunities identified
 3.2    1 volunteering program defined                                                          Achieved
        1 volunteering program implemented
 4.1    1 approval from Noosa Council secured to restore 2 trial restoration sites              Delayed
        2+ sites recovered with at least overall 80 m shore length of reef constructed
 4.2    1 approval from Noosa Council secured to restore an additional 2+ sites                 Delayed
        2+ additional sites recovered with at least an overall additional 600m 2 surface area
 4.3    1 related reef monitoring program established                                           Achieved
        2 six monthly status reports submitted                                                  On Track
        2 annual monitoring and evaluation report cards produced and published
 5.1    1 workshop facilitated                                                                  Achieved
 5.2    5 peer review reports submitted to Noosa Council during the three-year term of          On Track
        this Agreement, if requested by Noosa Council.
 5.3    3 study tours facilitated during the three-year term of this Agreement, if requested    On Hold
        by Noosa Council.
 5.4    1 Conservation Action Plan developed, as required                                       On Track
        1 set of Community Workshops facilitated, as required.
 5.5    1 new formal networking connections facilitated to assist Noosa Council with            On Track
        ongoing and future marine conservation activities, as requested
 5.6    1+ presentations given at national conference/s over 3 years                            On Track
        1+ presentations given at international conference/s over 3 years
 5.7    1+ New corporate/ government/ philanthropic alliances formed                            Achieved
        1+ New in-kind support/financial funding contributions secured
 5.8    1 Habitat mapping report, habitat suitability model, PhD study or similar output        Achieved
        completed and presented to Noosa Council




                                                                                                           11
Log in to download the original file

2022-04-12-P&E Agenda - Item 6 - Attachment 1 - TNC Noosa_Oyster Project _6_Monthly_Report(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.