Table 2: Total Progress to Date - Detailed

 Deliverables                   Measurable        Expected     Progress   Total progress to date and notes
                                outcomes          Timeframe
 (A1.1) A Technical Advisory    1 Technical       30 April     Achieved   Terms of Reference (ToR) for the
 Group (TAG) is established     Advisory Group    2020                    TAG finalised
 to provide project             with TOR
 oversight. This will include   established                               Inaugural meeting held 13 May
 a clear terms of reference                                               2020.
 (ToR) and consist of
 representatives from key                                                 TAG meetings are held as
 stakeholders (NSC, TNC,                                                  required and TAG members are
 Kabi Kabi and at least two                                               mostly engaged on a regular
 other independent                                                        basis out of session to advice on
 parties).                                                                specific aspects of the project
                                                                          (e.g. biosecurity, permits) and to
                                                                          review draft project reports.

 (A1.2) Appointment of          1 Project         31 January   Achieved   Craig Bohm appointed by TNC as
 dedicated project manager      Manager           2020                    Marine Coordinator for
 who is a marine biologist      appointed                                 Southeast Queensland, based in
 with extensive project                                                   Noosa. Position commenced 29
 management experience,                                                   January 2020.
 for the term of the
 Agreement.
 (A1.3) A Project               1 Project         31           Achieved   The project implementation plan
 Implementation Plan            Implementation    December                was endorsed by Noosa Shire
 detailing at a minimum:        Plan completed    2019                    Council as the ‘Project
 A detailed risk assessment     and endorsed by                           Management Plan’ at its
 associated with the            Noosa Council                             Ordinary Meeting held 16 July
 project.                                                                 2020. The Project Management
 A communications and           1 Detailed Risk                Achieved   Plan included a detailed risk
 media plan, outlining          Assessment                                assessment, Communications
 media protocols,               included                                  and Media Plan and Monitoring,
 opportunities, and the role                                              Evaluation and Reporting (MER)
 of TNC and NSC.                1                                         Plan.
 A monitoring, evaluation       Communications                 Achieved
 and reporting plan which       and Media Plan                            The MER Plan was then reviewed
 identified ecological and      completed                                 by an independent consultant
 social monitoring                                                        and the recommendations
 programs, how they will        1 Monitoring,                  Achieved   responded to and adopted by
 be reported on and how         Evaluation and                            TNC.
 this will fed-back into the    Reporting Plan
 project.                       completed

 (A1.4) Participation and       3 community       30 June      Achieved   Noosa Community Engagement
 delivery of public             engagement        2022                    Workshop
 education and                  forums
 engagement forums and          facilitated                               Public Information Sessions
 media statements
                                3 media                        Achieved   Produced and distributed:
                                statements
                                released                                  - Noosa Oyster Chronicle
                                                                                                               12
Log in to download the original file

2022-04-12-P&E Agenda - Item 6 - Attachment 1 - TNC Noosa_Oyster Project _6_Monthly_Report(PDF, 3MB).pdf · 3.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.