Demolition Decision Notice · OPW16/0051
Attached to the e-mail OPW16/0051 - Operational Works Application (REC15/0023).
12. Demolition waste must be transported and disposed in accordance with Council’s requirements.
Regulated waste (eg. asbestos) may require special disposal arrangements.
13. This approval does not authorise removal or damage vegetation within or adjacent to the subject
property (including street trees). Separate approval is required please contact Noosa Council for
further advice.
Certificates/ Documentation
14. The Building Certifier may require additional certification / documentation under certain
circumstances. The applicant will be advised if this is a requirement as the need arises.
Acceptability of certificates/documents is at the discretion of the Building Certifier, acceptance
of certificates is subject to the suitably qualified person being recognized as competent prior to
certification of the building element.
All certificates are to be submitted in the approved form (Form 16) or equivalent.
Local Authority Infrastructure
15. All services that may be affected by this construction shall be accurately located for alignment
and/or depth prior to commencement of works. Where sewer or stormwater access chambers are
located within the property they are to remain uncovered and accessible during and after
construction. Should difficulty arise in locating any service please contact Noosa Council Water
& Sewerage.
Codes for Self Assessable Development
The following self-assessable codes apply to this application
(1) Queensland Development Code
(2) National Construction Code 2014
(3) Building Removal & Demolition Code of the Noosa Plan.
Further Development Approvals Required:
Nil
The owner/applicant are advised that the following additional development approvals are or may be
required separately as part of the approval process.
1. Noosa Council Plumbing Approval.
Concurrence Agencies Conditions:
Nil.
Rights of Appeal
You may appeal against any matter stated in this Decision Notice. The appeal must be started within
20 business days (10 business days for building advice agencies), after the date this notice is given.
Extracts of your appeal rights under the SPA are attached.
Yours faithfully
Page 3 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Demolition Decision Notice.pdfRelated documentApplication case desk ↗
Demolition Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 186 KB (small file)
- File type
No other editions are linked here.