Assessment Managers Conditions:
General
Pursuant to the provisions of the Sustainable Planning Act2007 and the Building Act 1975 and made
thereunder, permission to undertake the building work as outlined above is subject to the following
conditions: -
1. All works subject to this approval are to be completed, inclusive of satisfactory final inspection
and submission of all associated certificates and documentation, no later than 6 months after the
date of approval or this approval will lapse.
Should this approval lapse, a new Development Approval for Building Works will be required
prior to continuance of any assessable development or inspection and will be subject to
compliance with legislative amendments that may have occurred in the interim period.
2. All conditions of this permit shall be complied with prior to the issue of a Form 21 - Final
Inspection Certificate.
3. The builder must ensure a notice of inspection is given to Noosa Building Certifiers (Ph. 5455
6081) before proceeding past the following stages of construction.
Mandatory Inspection Type Inspection to be undertaken by
Building General
A Final, on completion of all works relating to this Noosa Building Certifiers
approval.
B As may be required by the Building Certifier. Noosa Building Certifiers
Inspections will be undertaken in accordance with the Guidelines for the Inspections of Class 1
and 10 Buildings and Structures prepared by the Department of Local Government and Planning
(Qld) effective 14 November 2003.
4. All building work shall comply with the provisions of the Building Act 1975 and shall be in
accordance with the approval documents including any amendments or conditions shown in red.
5. Submission of a further application for approval of any proposed alteration or modification of
any drawing or specifications pertaining to this building approval.
6. A certified legible copy of the approved drawings and specifications is to be on the building site,
available for inspection by the Building Certifier at all times.
7. This Development Approval for Building Works does not incorporate the approval of any
sanitary drainage or plumbing works (Seal offs etc). Separate approval from your Local
Authority is required prior to commencing any such works.
8. Any excavation work required to remove footings etc. must be back filled and graded to natural
surface level in such a manner as to prevent the ponding of water. All other excavation and
filling is expressly prohibited.
9. At the completion of works, the site is to be clear of building and demolition waste, and left in a
tidy state with the complete building removed to ground level (inclusive of footings).
10. In sewered areas, house drainage is to be disconnected prior to the point of connection to
Council’s sewer by a licensed person.
11. Reticulated water supply is to be disconnected from the dwelling by a licenced person.
Page 2 of 6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Demolition Decision Notice.pdfRelated documentApplication case desk ↗
Demolition Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 186 KB (small file)
- File type
No other editions are linked here.