SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 NOVEMBER 2019
10 1819T085 - CONSTRUCTION OF HILTON TERRACE AND ERNEST STREET,
TEWANTIN: INTERSECTION AND CORRIDOR UPGRADE
DOCUMENT INFORM AT ION
Author Project Manager, Mark Poynter
Infrastructure Services Department
Index ECM \Projects(T1) \ Tewantin Hilton Terrace & Ernest Street – CAP.Work -
500679
ECM \Subject \Contracting \Contracts/Projects
Attachments 1. Tender Evaluation Report
EXECUTIVE SUMMARY
This report provides a recommendation for the contract award of the preferred contractor for
1819T085 Construction of the Hilton Terrace and Ernest Street, Tewantin: Intersection and
Corridor Upgrade.
RECOMMENDATION
That Council note the report by the Project Manager to the Services & Organisation Committee
Meeting dated 12 November 2019 and award Portion 1 & 2 of tender 1819T085 – Construction of
Hilton Terrace and Ernest Street, Tewantin: Intersection and Corridor Upgrade to PentaCon Pty
Ltd for the lump sum price of $2,809,954 (ex GST).
REPORT
The proposed contract is for the construction of a roundabout (and associated infrastructure) at
the Hilton Terrace - Ernest Street intersection and other improvements along the Hilton Terrace
corridor. This section of road is a known black-spot, has been identified as a priority project and
is up for renewal via the reseal program.
The contract works are proposed to commence onsite after Australia Day 2020 with the majority
of the work to be completed prior to the Easter 2020 holidays.
1. Design
The design for these works has been through multiple iterations and reviews to seek the most
economical outcome. The aim of the project was to improve traffic movements at the Hilton
Terrace - Ernest Street intersection, provide on-road cycle facilities on Hilton Terrace (connecting
to adjacent facilities) and generally improve amenity and safety for residents and road users.
Page 34 of 129
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.