Skip to the record
The only place to find full transcripts.

Original source · versioned page text

2019-11-12 Services & Organisation Committee Agenda

of 129

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (11.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

SERVICES & ORGANISATION COMMITTEE MEETING AGENDA                                       12 NOVEMBER 2019


10                       1819T085 - CONSTRUCTION OF HILTON TERRACE AND ERNEST STREET,
                         TEWANTIN: INTERSECTION AND CORRIDOR UPGRADE
DOCUMENT INFORM AT ION




Author                            Project Manager, Mark Poynter
                                  Infrastructure Services Department

Index                             ECM \Projects(T1) \ Tewantin Hilton Terrace & Ernest Street – CAP.Work -
                                  500679
                                  ECM \Subject \Contracting \Contracts/Projects

Attachments                       1.   Tender Evaluation Report



EXECUTIVE SUMMARY
This report provides a recommendation for the contract award of the preferred contractor for
1819T085 Construction of the Hilton Terrace and Ernest Street, Tewantin: Intersection and
Corridor Upgrade.

RECOMMENDATION
That Council note the report by the Project Manager to the Services & Organisation Committee
Meeting dated 12 November 2019 and award Portion 1 & 2 of tender 1819T085 – Construction of
Hilton Terrace and Ernest Street, Tewantin: Intersection and Corridor Upgrade to PentaCon Pty
Ltd for the lump sum price of $2,809,954 (ex GST).


REPORT
The proposed contract is for the construction of a roundabout (and associated infrastructure) at
the Hilton Terrace - Ernest Street intersection and other improvements along the Hilton Terrace
corridor. This section of road is a known black-spot, has been identified as a priority project and
is up for renewal via the reseal program.

The contract works are proposed to commence onsite after Australia Day 2020 with the majority
of the work to be completed prior to the Easter 2020 holidays.

1.                       Design

The design for these works has been through multiple iterations and reviews to seek the most
economical outcome. The aim of the project was to improve traffic movements at the Hilton
Terrace - Ernest Street intersection, provide on-road cycle facilities on Hilton Terrace (connecting
to adjacent facilities) and generally improve amenity and safety for residents and road users.




                                                                                            Page 34 of 129
Log in to download the original file

2019-11-12 Services & Organisation Committee Agenda(PDF, 11MB).pdf · 11.0 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.