SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 12 NOVEMBER 2019
SAFETY RISKS MITIGATION
This is a high risk project due to proximity to traffic Prior to construction commencing, work place
and pedestrians. health and safety and pedestrian and traffic
management plans will be required to be
submitted to Council for review. Regular audits on
contractor compliance with these approved plans
will be undertaken by Council throughout
construction.
ENVIRONMENTAL HARM RISKS MITIGATION
There is risk that the works do impact on existing Council has engaged an independent arborist to
mature vegetation. ensure that mature trees are protected and the
construction methodology to ensure impacts are
minimised
Risk of spills from materials. Contractors are required to have an environment
management plan which will be reviewed and
approved by Council prior to commencement.
SCOPE AND QUALITY RISKS MITIGATION
Risk of not meeting project objectives To be managed through Council staff ensuring the
original design and specifications are met.
PUBLIC DISRUPTION AND COUNCIL MITIGATION
REPUTATION RISKS
Noise from plant and equipment may be a cause This will be minimised where ever possible.
of disruption to local residents.
Vibration Contractors will be required to meet established
specifications regarding vibration works.
Amenity of the site reduced by construction Propose to appropriately screen construction
process and not acceptable for the location. fencing and work areas.
Consultation
External Consultation - Community & Stakeholder
Local residents have and will continue to be informed via letter drop of the timing and impact of
the construction activities.
Internal Consultation
Departments/Sections Consulted:
X Chief Executive Officer Community Services X Corporate Services
Executive Officer Director Director
Executive Support Community Development X Financial Services
Community Facilities ICT
Libraries & Galleries X Procurement & Fleet
Local Laws Property
Waste & Environmental Health Revenue Services
X Executive Services X Environment & Sustainable Development X Infrastructure Services
Director Director Director
X Community Engagement Building & Plumbing Services X Asset Management
Customer Service Development Assessment Buildings and Facilities
Governance Economic Development X Civil Operations
People and Culture X Environmental Services Disaster Management
Strategic Land Use Planning X Infrastructure Planning,
Design and Delivery
Page 39 of 129
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.