NOOSA COUNCIL IDAS Development Application Decision Notice                                                      9

63.    Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP28 and PSP30
       on Water Supply Headworks Contributions and Sewerage Headworks Contributions respectively and at
       the rates applicable at the time of payment. An estimate only of the contribution rates under the current
       policies is outlined below. These amounts will adjusted in line with changes to the Consumer Price Index,
       All Groups Brisbane from December 2004 until the date of payment.
       Water Supply         $8,060
       Sewerage             $7,340
       TOTAL                $15,400
       All headworks contributions must be paid prior to the issue of a Development Permit for Operational
       Works.
       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the headworks
       contributions not be paid at the due time, Council shall call upon the trading bank guarantee in full.
       In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
       the contribution or trading bank guarantee will be returned.
Earthworks
64.    Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s Engineering
       Design Standards Manual and so as not to cause additional ponding of water on any adjoining lands or
       the blockage of, or interference with, any natural watercourses. Detailed site surveys indicating natural
       surface levels and contours of the adjoining properties must be provided with the application for a
       Development Permit for Operational Works for Filling and Drainage.
       This may require the design and construction of drainage pipes and/or an overland flow-path within the
       development site that caters for drainage from the adjoining sites for a design storm with an Average
       Recurrence Interval of 1 in 100 years. A private easement for the Drainage of Water encompassing the
       drainage pipes or overland flow-path will also be required. In this regard a Development Permit for
       Operational Works shall be obtained.
       Should evidence be provided to Council indicating that No Ponding of stormwater will occur on the
       adjoining properties the requirement for the drainage pipes, overland flow-path and easement shall not
       apply.
65.    Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
       structures that border the development site. Fences that are affected shall be replaced prior to plan
       endorsement. In this regard any fences to be replaced shall be clearly shown on the plans submitted for
       Operational Works approval.
Site Stability
66.    A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site, determine the
       soil classification, establish whether any measures are required to protect the stability of adjoining
       buildings and/or structures, and make recommendations on the type of foundation system(s) best suited
       for the proposed development. This information shall be submitted to the Council for assessment and
       approval prior to obtaining a Development Permit for Operational Works.
Erosion and Sediment Control
67.    Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
       control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
       waste, will be necessary.
     In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
     to the Council for approval prior to obtaining a Development Permit for Operational Works.
General
68.    A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
       specifications for all engineering works that will become Council infrastructure including Council’s
       easements, which shall be submitted in conjunction with an application for a Development Permit for
       Operational Works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre
       layout is to be submitted in conjunction with any application for Operational Works.

69.    Digital detailed design drawings and calculations shall be submitted with any application for a
       Development Permit for Operational Works in respect of roadworks and stormwater drainage works. To
       avoid conflict with underground pipes or services, all existing and proposed services required by the
       development shall be shown on the plans.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@e808d94f\@[email protected]

Used in these records

About this file

File size
71 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

00155818.001.pdf · 71 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.