Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published) · MCU24/0153

of 22

Text shows just the words. Original shows the document exactly as it was published.

                           041               B       Stormwater Catchment Layout                26        August
                                                                                                2025
                                                     Prepared by RECOR

                           044               A       Stormwater Details                         26        August
                                                                                                2025
                                                     Prepared by RECOR

                           LD1               F       General Notes, Sheet Layout & Site 02/12/2025
                                                     Location prepared by Anembo Consultants

                           LD2               F       Project Specifications prepared by Anembo 02/12/2025
                                                     Consultants

                           LD3               F       Project      Specifications,    Annual 02/12/2025
                                                     Maintenance    &     Finishes Schedule
                                                     prepared by Anembo Consultants

                           LD4               F       Plant Schedules prepared by Anembo 02/12/2025
                                                     Consultants

                           LD5               F       Typical Details prepared by Anembo 02/12/2025
                                                     Consultants

                           LP1               F       Landscape Plan (Ground 1/2) prepared by 02/12/2025
                                                     Anembo Consultants

                           LP2               F       Landscape Plan (Ground 2/2) prepared by 02/12/2025
                                                     Anembo Consultants

                           LP3               F       Landscape Plan (First Level) prepared by 02/12/2025
                                                     Anembo Consultants

                           LP4               F       Landscape Plan (Second Floor) prepared 02/12/2025
                                                     by Anembo Consultants

                           LP5               F       Landscape Plan (Roof)       prepared   by 02/12/2025
                                                     Anembo Consultants

               Currency Period
               2.     This development approval lapses if the requirements of the conditions have not been
                      completed and lodged with Council by 11 August 2027, unless an application to extend the
                      currency period is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Bonds
               3.     A site control and/or compliance bond of $10,000 is to be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               4.     Bonds must:
                      a.      meet the requirements of Council’s relevant Planning Scheme Policy for performance
                              and uncompleted works;



                                                                                                   Page 9 of 22
Document Set ID: 24037249
Version: 8, Version Date: 18/12/2025

Used in these records

About this file

File size
221 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice MCU24 0153 & OPW24 0202 (As Published).pdf · 221 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.