Risk Mitigation
To mitigate the determined risks that have been identified in the TRAQ assessment
we as the Project Arborist shall,
   1. Perform weight reduction pruning as per AS 4373-2007 to try and alleviate the
      weight disparity.
   2. Set up a monitoring system to monitor tree/trunk movement. This shall be
      achieved by the installation of a plumb bob and stringline attached to the tree
      on the downhill side of the tree and an installed board with markings on it of
      the date and time of measurement. We shall also measure from a marked
      point on the plumb to the trunk of the tree as a control also. This shall be
      monitored monthly throughout the project and reviewed once the project is
      completed.
   3. Regular inspections at monthly intervals or at critical stages of the project that
      encroach on the SRZ of the tree in question and using TRAQ to assess if
      deemed suitable.
   4. Supervise and create a tree protection methodology regarding the landscape
      plantings and the remainder of the building works.
We have identified that there is a determined risk with the retention of this tree on this
site, on this slope and in this growing medium. There have been significant site
changes:
   1. Large trees have been removed uphill in the neighbouring property and these
      were dead or in decline and although there was limited foliage they were
      covered in a unknown vine species that offered limited protection. With this
      now removed exposure has increase on a limited scale from both weather
      from the S/SE direction. Also, this has increased on a minor scale rain onto
      the root plate of Tree 28.
   2. Excavation up to the SRZ and piles were installed there may have been minor
      root damage but still outside the SRZ. This excavation was approximately
      2.75m away from Tree 28 base which is just outside the SRZ and is on the
      uphill (tension side) S/SW. Although this potentially may have severed minor
      fibrous roots outside the SRZ the effect on Tree 28 is inconsequential and
      should not have altered the trees stability and integrity in its current position.

With these changes in mind, we as the PA will monitor and manage the risk and
report on this using the mitigation system provided.
In relation to Landscape and plant installation within the determined SRZ we direct
that all these works are to be supervised by the PA and no mechanical digging shall


 “We manage the trees that you care about and remove the trees you worry about”

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Approved Plans OPW17_0561.01.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.