Compiled Approved Plans OPW17/0561.01

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Amendment 6:
1.
a.      No further works, machinery or storage of materials will be located within the undeveloped
portion of the Tree Protection Zone of Tree 28, the Endiandra sieberi (Corkwood), located
immediately north of the proposed lift access walkway entrance.
b.      Recommendations laid out in AS4970-2009 Protection of trees on development sites will
be adhered to throughout the remaining build under the supervision of and certification by the
project arborist Kurt Brown.
c.      A Tree Protection Zone as per AS4970 requirements will be established.
d.      Tree 28, the Endiandra sieberi (Corkwood), will be monitored and protected from
construction activities in accordance with the approval conditions noted in this revised construction
management plan and the existing operational works approval updated to include the following:

i.     an advanced arboriculture inspection of the root plate and collar in accordance with the ISA
Tree Risk Assessment procedure will be undertaken by project arborist Kurt brown in the company
of Council’s delegate.
The permit applicant will meet the reasonable cost of Council’s delegate attending the inspection.
ii.    landscaping works within the tree protection zone will be undertaken under the direction of
the Project Arborist Kurt Brown.

2. Install 350-4500 grout piles with micro pile to a minimum depth of 1.5m below tunnel floor and
lift over run.

3. Build concrete capping beam 500mm deep x 800mm wide and install concrete beam (SB) to
span between tunnel walls.

4. Excavate down 2.5 m maximum at end of tunnel/ lift shaft using a 1.5t mini excavator
established between the rows of grout piles directly above the area to be excavated. The
excavated material to be loaded directly onto portable soil conveyors installed downslope of the
excavator to covey the material to the area previously excavated for the terrace deck. Sufficient
material to be retained at this level to back fill over tunnel slab to level of existing adjacent ground
slope.

5. Surplus excavated material to be disposed of in the same manner as the previously excavated
terrace deck using a series of soil conveyors supported by the existing scaffold platforms, directly
to a light truck situated adjacent to the garage of No. 10 Park Road and removed from site in small
loads as work proceeds.

6. Install temporary steel "UC" Shoring after grouting and waterproofing behind horizontal whaler.

7. Excavate further 2.5 m maximum at end of tunnel / lift shaft and install temporary steel "UC"
Shoring and repeat until excavation reaches the lift overrun.

8. Construct lift base footing and tunnel base footing after installing steel reinforcing and starter
bars for the walls

9. Spray first shotcrete wall to give flat surface after water blasting grout piles, Install waterproofing
membrane.

10. Install steel reinforcement to walls and Shotcrete walls up to underside of tunnel slab (Use
40mpa Concrete)

11. Construct tunnel slab and install waterproofing protection and drainage.

12. Install steel reinforcement to remaining walls and Shotcrete up to underside of capping beam

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Approved Plans OPW17_0561.01.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.