Compiled Approved Plans OPW17/0561.01

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
leaving starter bars for block work lift shaft. (Use 40mpa Concrete)

13. Build blockwork lift shaft to roof level and cut out and repair 150 UC struts

14. Construct Block Balustrade to Tunnel

15. Back fill over tunnel slab and landscape to level of existing adjacent ground slope reusing sand
retained from excavations conveyed to backfilled area reversing the system used for excavation.
The Sand is retained by the previously installed shotcrete piers, pier caps and tunnel balustrade.
Sand to be placed in 300mm layers watered in and compacted with a plate vibrator as work
proceeds returning the soil to existing compaction levels maximizing slope stability. Long term
slope stability will be maintained by the establishment of trees and shrubs in accordance with the
Myles Baldwin Design report listed in the decision notice and updated Myles Baldwin Landscaping
plan which has been revised for compliance with the approval conditions.

16.    Install rock face over blockwork lift shaft and tunnel.

17.    Install lift and concrete roof over lift shaft.

18.      The works shall be landscaped generally in accordance with the Myles Baldwin Design
report listed in the decision notice and updated Myles Baldwin Landscaping plan which has been
revised to include the following information specifically required in the of the approval conditions.

a.       Details of local native tree and understory species to be installed to the site including
upslope of Tree 28, the Endiandra sieberi (Corkwood) and over the access tunnel.
b.       Methods to be engaged in the establishment and maintenance of the required landscaping
in conjunction with any arborists recommendations.
c.       Details of reinstatement of the soils to the roof of the access tunnel and methods to ensure
slope stability in both short-term and long term. (Also see Item 15 above and the included Slope
stability certification)
d.       Landscaping details to ensure the development is visually screened with vegetation when
viewed from Main Beach by maintaining and enhancing the existing canopy structure.

A copy of the revised landscaping plan is attached along with this revised construction
management plan in order to include as a revision of the existing operational works approval.

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Compiled Approved Plans OPW17_0561.01.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.