Original source · versioned page text
Approved Plan - OPW230084
Plans and drawings: the text below has words only, no drawings.
• The FSC will:
o inspect each of the potential habitat features (usually hollows, dreys and
arboreal termite nests) to determine the presence of arboreal fauna. This is
carried out by simply looking into hollows with the assistance of a small
torch, however, burrow and bore-scopes can also be useful for deep
hollows.
o If fauna is located within a hollow, a towel or rag will be firmly lodged into the
entrance to prevent wildlife from experiencing additional distress or
attempting to escape due to a perceived threat.
o If an occupied Ringtail possum drey is encountered, the FSC should quietly
approach (i.e., avoid contacting other branches) the drey in the EWP bucket
and physically capture the possum by placing the entire drey in a catch bag
or only the possum if it emerges from the drey.
o Once the hollow entrance has been secured the arborist or FSC will cut the
entire hollow limb off below the cavity where the branch remains solid. In
circumstances where a hollow continues into the main stem of the tree, a
small window will be carefully cut into the hollow, allowing the FSC to plug
the hollow above and below the window.
o When the fauna has been safely secured within its hollow, the entire limb
can then be placed in the EWP bucket or lowered to the ground using ropes.
o This limb will then be placed in a cool, quiet location until translocation to the
recipient habitat Site, when at dusk the hollow entrance is re-opened to
allow the fauna to emerge of its own accord.
• If there is more than one work zone undertaking clearing or earthworks, there is
the requirement for at least one FSC per work front.
• Undertake sequential clearing - the direction of sequential clearing should be
away from road infrastructure and threatening environments, and towards
habitat links to ensure fauna are not moving through disturbed areas (Figure 7).
• Trees to be cleared along the boundary of the VPZ are to be felled inwards to
avoid damaging surrounding retained vegetation.
• All trees to be removed will be rechecked by a FSC prior to and after felling, to
ensure there is no fauna present.
• All trees that are to be stockpiled overnight must be re-checked by the FSC prior
to mulching to ensure no fauna have relocated into the pile.
After works:
• Fauna should not be left in an isolated ‘island’ of habitat unless there is no other
option suitable.
• Cleared vegetation should be piled thoughtfully; kept away from waterways and
without causing damage to the surrounding habitat.
• Cleared vegetation must be piled in a way that will not disturb fauna movement.
• Large rocks and logs must be removed and placed in nearby vegetation to
provide shelter for fauna.
• Ongoing erosion controls must be in place to reduce erosion and sedimentation
into the watercourse.
Performance 1. Zero disturbance must occur outside the permitted clearing area.
indicators 2. Mortality and disturbance of fauna should be prevented.
Personnel Base Architecture is held accountable for:
responsible
• Ensuring all contractors have read and are able to comply with this
management plan.
• Ensuring a suitably qualified FSC undertakes a Pre-Clearance survey to identify
habitat features and reduce fauna load within two [2] weeks of clearing works.
• Ensuring a suitably qualified FSC is present for all vegetation clearing.
FAUNA MANAGEMENT PLAN | Summit Road, Pomona
20
Document Set ID: 22570982
Version: 1, Version Date: 05/09/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.