D194/2014 - Sealed Order
UNITYWATER
The following Unitywater conditions are applied in accordance with the South East
Queensland (Distribution and Retail) Restructuring Act 2009 and Unitywater's Interim
Connections Policy. The conditions below form part of a water connection aspect which are
taken to be a water approval for a staged connection. Any future applications must be made
to Unitywater under South East Queensland (Distribution and Retail) Restructuring Act 2009.
Unitywater can be contacted as foliows;
Phone; 1300 0 Unity (1300 086 489)
Email: [email protected]
Web: www.unitvwater.com
Water <£ Sewerage
22. Reticulated water supply and sewerage must be provided to the development.
23. Construction activities must not impede the access of Unitywater or Fire Brigade
personnel to vital infrastructure (eg. valves, fire hydrants and sewer access chambers).
24. The fire-fighting demand on Unitywater's water supply system from the development
must not exceed 30 litres per second.
25. A single Unitywater installed primary water meter must be provided immediateiy inside
the property boundary. Meters must be Unitywater approved, installed in accordance
with Unitywater requirements and remain accessible at all times for reading and
maintenance purposes,
26. Water meters must be located on alternative boundaries to electrical pillars.
27. Buildings, basements and other structures must maintain a minimum clearance of 1.5
meters from Unitywater sewer mains, and 1.0 meter from a sewer manhole chamber
or sewer inspection opening.
28. Easements of between 3 and 10 metres must be provided over all Unitywater sewers
located within property boundaries in accordance with the SEQ standards. Easements
shall be centred over the pipe. Easement terms shall be the most current registered
dealing held by the Department of Natural Resources & Mines and shall not be altered
or amended.
29. Storm water retention systems and gross pollutant traps must maintain a minimum
clearance of 1.5 meters from Unitywater water supply and sewerage infrastructure.
30. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
Unitywater water mains and 1.5 metres from Unitywater sewerage mains. Landscaping
plants within these clearances must be low growing when mature, and suitable
approved varieties.
31. Construction works undertaken in the vicinity of Unitywater water supply or sewerage
infrastructure must not adversely affect the integrity of the infrastructure. All costs
associated with repair, replacement or alteration of infrastructure must be met by the
applicant.