Decision Notice · 142006.932
NOOSA COUNCIL IDAS Development Application Decision Notice 06/0932 16 May 2006 3 of 7
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
This Decision Notice is issued subject to and conditional upon the relevant Approved Development Permit having been
granted to the applicant.
Special Conditions
1. Proposed sewer is located within a layer of peat and as such requires additional bedding and support to guarantee
integrity of the system. Method of sewer support must be submitted and approved by Water & Sewerage Capital
Works Manager prior to commencement of works on-site.
2. Appropriate silt and sediment control devices to be in place prior to commencement of works.
3. Dewatering - Council will allow discharge of the dewatering process to existing Council sewers which discharge to
Pump Station NV2 in Mill Street providing rate of discharge does not impose any detrimental effects on the
sewerage pump station. Council’s Sewerage Pump Station Foreman, Martin Pratt, Ph. 5440 9136 shall be
contacted to arrange appropriate monitoring of process.
Should rate of discharge be unsuitable, the dewatering process is to cease immediately and alternative
arrangements made for treatment and disposal of water produced.
4. Acid sulphate soils management plan to be approved prior to commencement of works.
1. A copy of the job specification is to be provided to Council’s Inspector within seven (7) days of the date of this Decision
Notice, and prior to commencement of works.
2. The names of any proposed contractors for works are to be submitted in writing, together with copies of current Public
Liability and Workers Compensation Insurances together with certificates of currency for those policies, for consideration
by the Assessment Manager seven (7) days prior to pre-start meetings and commencement of works.
A separate letter will then be issued approving the contractor (or otherwise) for the works. No other contractor or
subcontractor shall be engaged to carry out the works or any part of the works without the written approval of the
Assessment Manager.
3. Council’s Water & Sewerage Inspector shall be given (7) days notice of intention to commence works. A pre-start
meeting shall be arranged prior to commencement of works by contacting Council’s Water & Sewerage Inspector, Mr
Trevor Mourilyan, Ph. 0417 780 830. Inspector is only available for pre-start meetings, inspections and testing etc.
between the hours of 6:30am to 4:00pm, Monday to Friday. Inspector will not be available outside these hours unless
prior approval is obtained from the Water & Sewerage Capital Works Manager with any costs incurred by Council outside
the hours nominated above, met by the Contractor/Developer. These costs will be in addition to normal inspection fees.
4. Notwithstanding that Council has checked the plans with due care, where it is found during construction that variations
exist with Council's standards, Council standards shall apply.
5. It is the responsibility of the applicant to ensure that its consultants and contractors take all reasonable care during the
construction of the engineering works to ensure that Council property or facilities (such as underground drainage, water
supply and sewerage) are protected against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the applicant or any of its consultants or contractors through
any cause whatsoever in the course of, directly or indirectly, carrying out the engineering works, the applicant and/or its
contractors shall forthwith notify the Assessment Manager and shall forthwith rectify the damage to that property or
facility at its cost to the satisfaction of the Assessment Manager prior to the sealing of the survey plan and/or acceptance of
the works on-maintenance. Alternatively, the applicant may request the Council to carry out the rectification work at the
applicant's cost, such cost being paid by the applicant to the Council prior to the sealing of the survey plan and/or
acceptance of the works 'on maintenance' provided that in the case of emergency, the Council shall be entitled to rectify
such damage at the cost of the applicant such cost being paid prior to the sealing of the survey plan and/or acceptance of
the work 'on maintenance'.
6. The Contractor shall make all necessary arrangements for supply of water required for construction works. The use of
hydrant standpipes on Council mains will NOT be permitted. Contractors should contact Council’s Water Section on
phone 5449 5254 to obtain an application form for issue of a key to access Council’s water tanker filling stations.
Conditions of access and location of filling stations are detailed on the application form.
AB c:\users\abecker\downloads\ecm_9956525_v1_decision notice.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 337 KB (small file)
- File type
No other editions are linked here.