Decision Notice · 142006.932
NOOSA COUNCIL IDAS Development Application Decision Notice 06/0932 16 May 2006 4 of 7
7. All sewerage reticulation mains are to be inspected by closed circuit television (CCTV) prior to acceptance 'on
maintenance'.
CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council following satisfactory
completion of construction works. The developer will be responsible for the full cost of CCTV inspection, including any
additional inspection necessary following defect identification and rectification . This charge is payable prior to
commencement of works and will be determined on the unit rate basis current at the time of approval.
8. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform Traffic
Control Devices and Main Roads Department Roadworks Signing Guide.
9. As Constructed drawings in both hardcopy and digital format (ADAC) to the standards and requirements of the
Assessment Manager are required for Council records. Such 'as constructed' drawings will be required prior to works
being accepted "on maintenance", where applicable. Requirements for "as constructed" information are detailed in the
current version of Council's Engineering Design Standards (Water & Sewerage) Manual.
Release of plans of survey and/or acceptance of the works on-maintenance will not be considered until lodgement of
satisfactory 'as constructed' records.
Please note that bonding of outstanding works will not be considered by Council.
10. The Consulting Engineers for the project, Callaghan & Toth, are responsible for arranging all inspections and ensuring that
all relevant details required by Council are supplied. The attached Water and Sewerage Inspection Report form is to be
kept by you and presented to Council's Inspector at each stage of the development requiring a meeting or inspection. The
Inspector will sign the form at each stage when conditions have been satisfied. The works will be accepted 'on
maintenance' when this form, signed by the Inspector for each stage, is returned with a letter requesting that it go 'on
maintenance'.
11. It is Council policy that a maintenance bond be imposed on construction works during the maintenance period. The
maintenance bond shall be 5% of the agreed value of the development obligations, or $1,500 whichever is the greater
amount. This bond must be lodged by (and shall only be accepted from) the Developer for the works.
12. Construction work and other associated activities are permitted only during the hours of 7:00am and 6:00pm Monday to
Saturday. No work is permitted on Sundays or public holidays, except where extended hours are approved by the
Assessment Manager or his nominee.
13. Cut-ins to existing live sewer are to be performed by Approved Contractor. Noosa Council Works Inspector shall be
present during any work on live sewer undertaken by contractor. An additional fee of $140.00 (included below) is
required to cover costs associated with these live sewer works.
14. Fees applicable to the above project are listed below:-
Plan Examination $ 710.00
Inspection Fee $ 710.00
Checking as-constructed data $ 120.00
CCTV fee $ 420.00
Live sewer inspection $ 140.00
BALANCE $ 2,100.00 (Journalled from Job No.195850 - 16.05.06)
Copies to -
WSI-1 - please note the approval of attached plans.
AOD-2 to note
CTOD
AB c:\users\abecker\downloads\ecm_9956525_v1_decision notice.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 337 KB (small file)
- File type
No other editions are linked here.