                                                                                         15104 - SBSMP/0
                                                                                                  Page 10




5.3 XP-RAFTS Detention Analysis
XP-RAFTS has been used to model the peak discharges from the site under both existing (pre
development) and proposed (post development) conditions, and to determine the sizing
requirements of the detention basin as outlined in Section 5 of the QUDM.

5.3.1 Pre Development
Figure 5.1 shows the XP-RAFTS model used to represent the pre development site conditions
and Table 5.4 summarises the input parameters used in the model for the pre developed site
scenario.




                             Figure 5.1 - XP-RAFTS Pre Development Model

                  Table 5.4 - XP-RAFTS Source Node Parameters – Pre Development
                                                              Pre Development
                                                                 Pre-D Site
                              Parameter
                                                    Sub Catchment 1 Sub Catchment 2
                                                       (Pervious)         (Impervious)
                          Initial Loss (mm)                10                 N/A
                      Continuous Loss (mm/hr)              2.5                N/A
                        Catchment Area (ha)              0.147                N/A
                       Impervious Percentage               0%                 N/A
                            Vectored Slope               16.8%                N/A
                             Manning's "n"               0.045                N/A
                           IFD Coefficients          Sunshine Beach           N/A
                         Storage Coefficient              N/A                 N/A


Table 5.5 summaries the pre development peak flows calculated by XP-RAFTS for a range of
design storms. For reference, the peak flows calculated using the Rational Method have also
been provided in Table 5.5.




Site Based Stormwater Management Plan
Residential Development at 43 Elanda Street, Sunshine Beach

Used in these records

About this file

File size
4.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

15104 - SBSMP - Rev 0.pdf · 4.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.