Table 5.7 summaries the post development unmitigated peak flows calculated by XP-RAFTS for
a range of design storms. For reference, the peak flows calculated using the Rational Method
have also been provided in Table 5.7.
Table 5.7 – Post Development Peak Discharge (XP-RAFTS and Rational Method)
XP-RAFTS RATIONAL METHOD
ARI Post Development Peak Discharge Post Development Peak Discharge
(years) (Unmitigated) (Unmitigated)
(m3/s) (m3/s)
0.052
1 0.032
(1yr 25min storm)
0.066
2 0.043
(2yr 25min storm)
0.082
5 0.059
(5yr 25min storm)
0.091
10 0.069
(10yr 25min storm)
0.104
20 0.083
(20yr 25min storm)
0.111
50 0.105
(50yr 20min storm)
0.122
100 0.121
(100yr 20min storm)
As seen in Table 5.5 and Table 5.7 there will be an increase in peak flows from pre to post
development conditions as a result of the proposed development. Consequently on-site
detention will be required.
For XP-RAFTS post development unmitigated peak flow rate hydrographs refer to Appendix F.
It is noted that the percentage increase in peak flows for the Rational Method are in the order
of 36% and for the Laurenson Method (used in XP-RAFTS) 2%-19% for minor storms and 2%-4% for
major storms. This difference can be explained by the fact that XP-RAFTS is a non-linear
routing hydrologic model which calculates flood hydrographs from storm rainfall hyetographs.
The Laurenson Method also specifically accounts for slope and other parameters while allowing
for storage within the catchment. The Rational Method combines parameters into one runoff
coefficient used to calculate the peak flows and does not provide for specific parameters (e.g.
slope, manning’s “n” etc).
5.3.3 Post Development Mitigated
Stormwater detention will need to be provided to ensure the pre development peak flows listed
in Table 5.5 are not exceeded for the proposed development. The detention storage is to be
implemented as part of the internal stormwater drainage network. The legal point of discharge
described in Section 4.3 will remain.
Site Based Stormwater Management Plan
Residential Development at 43 Elanda Street, Sunshine Beach
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
15104 - SBSMP - Rev 0.pdfRelated documentApplication case desk ↗
15104 - SBSMP - Rev 0.pdfRelated documentApplication case desk ↗
15104 - SBSMP - Rev 0.pdfRelated documentApplication case desk ↗
15104 - SBSMP - Rev 0.pdfRelated documentApplication case desk ↗
About this file
- File size
- 4.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.