12. APP G. Stormwater Management Plan

Attached to the e-mail MCU14/0102 Development application Part 3 of 4 App G Stormwater Management Plan.

of 62

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 19, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
          Figure 6.2: Bio-Retention Basin Typical Cross-Section (courtesy of Healthy Waterways)


          MODELLING OF THE DEVELOPMENT SITE
          (MUSIC)
          Modelling of the site was undertaken using the ‘Model for Urban Stormwater Improvement
          Conceptualisation (MUSIC)’ as promoted by the Noosa Council and the South East Queensland
          Healthy Waterways Partnership. The development was modelled using the split catchment
          approach. An appropriate type of land use was applied to all surface types within the developed
          catchments; with individual treatment devices assigned the relevant modelling treatment
          parameters. Consequently, a treatment train was established for each catchment, ensuring that
          all water discharging from site adheres to the specified Water Quality Objectives.

          Meteorological data for input into MUSIC was obtained for the greater Caloundra catchment
          from the Bureau of Meteorology. Six minute time step rainfall data was obtained for the climate
          period from 1/1/1980 to 31/12/1989. The catchment parameters of the MUSIC modelling are
          specified within the South East Queensland Healthy Waterways Partnerships’ Water by Design
          MUSIC Modelling Guidelines for South East Queensland Version 1 (2010), and have been
          modelled as such.

          POLLUTANT SOURCE NODE DETAILS
          Tables 6.2 and 6.3 show the pollutant source node parameters input into the MUSIC model.
          These parameters have been utilised in accordance with the South East Queensland Healthy
          Waterways Partnerships’ Water by Design MUSIC Modelling Guidelines for South East
          Queensland Version 1 (2010).

          Table 6.2: Rainfall – Runoff Parameters
           Storage Capacity (mm/day)                        18
           Initial Storage (%)                              10
           Field Capacity (mm)                              80
           Initial Depth (mm)                               50
           Daily Recharge Rate (%)                           0
           Daily Baseflow Rate (%)                          31


                                                                                           Stormwater Management Plans
Page 12                                                                      Hyder Consulting Pty Ltd-ABN 76 104 485 289
                                         f:\aa007595\f-reports\f0002-aar-aa007595 sbswmp report\f0002-aa007595-aar-03.-smp.docx
Log in to download the original file

12. APP G. Stormwater Management Plan.pdf · 6.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.