Original source · versioned page text
response to information request Plover St
12.5. The location of any services, above or below ground, adjacent to the
proposed walls.
13. Provide a preliminary Stormwater Management Plan for the site, including
details of collection and discharge of stormwater runoff from the buildings
and the hardstand areas.
A copy of the geotechnical report, structural plans of retaining walls by Lindsays
Consulting Engineers is attached recommending construction techniques. Preliminary
stormwater pits and locations are provided on the site plan which is in accordance with
the recommendations of the requirements of the geotechnical plans for all water to be
directed to Tristania Dr.
---------------------------------------------------------------------------------------------------------------------
Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the information requested in the information request. Please proceed with the
assessment of the application at your earliest convenience.
If you have any further queries in relation to the above, please do not hesitate to contact
myself.
Regards,
Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA MQELA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Page 5 of 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.