PART Response to Information Request · OPW11/0335
Very large file (26.7 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
1. As per stage 1, without the swale for the capture of sheet-flow from the northern
catchment areas
6.3 Modelling of the Stormwater Treatment Train
Version 4 of the Model for Urban Stormwater Improvement Conceptualisation (MUSIC
v4) has been utilised to predict the performance of the proposed stormwater treatment
train. The use of Version 4 of the MUSIC model has been maintained due to the timing
of the submission of the original application (prior to the release of Music V5). Modelling
for both Stage 1 only and the complete development has been conducted to ensure that
the proposed treatment system will be effective at all stages.
Music model parameters have been developed and agreed to by the stormwater experts
(David Bristow and Neil Collins) as part of the Planning and Environment court appeal
(Appeal No: 2587 of 2008) concerning the development.
In addition to load reduction predictions a 'no worsening' case has been applied,
comparing the predicted discharge from the undeveloped site with the development
stages.
6.3.1 Existing Development
The site is presently developed as a caravan park (the Peregian Beach Caravan Park),
with approximately two thirds of the existing site being cleared for caravans and
camping, consisting of mown grass under a light canopy of Broad-leaved Paperbark
(Melaletica quinquenerva).
Land uses in the Peregian Beach Village area surrounding the proposed development
site includes retail and businesses, sporting facilities, a kindergarten, and the Noosa
National Park.
There is currently no stormwater quality improvement or treatment devices installed at
the existing caravan park. Modelling has been conducted to provide a baseline to allow
the comparison of the performance of the developed stormwater system to the existing
case. The stormwater system must achieve both the quality objectives in Table 3-1 and
a no worsening' of pollutant loads on the national park.
Table 6-2: MUSIC Model Results - Undeveloped Site
Water Quality Indicator Result
Estimated long-term load (kg/year) % reduction Load (kg/year)
Suspended Solids 0 2170
Total Phosphorus 0 5.1
Total Nitrogen 0 30
6.3.2 Stage I Modelling
Results of MUSIC modelling showed that there will be no net increase in stormwater
runoff from the site. Loads of sediment, total nitrogen and total phosphorus will be
substantially removed from stormwater before entering the Noosa National Park
(Appendix B).
Modelling for the Stage 1 development predicted a 15% reduction in stormwater entering
Noosa National Park, from 13.1 ML/year to 11.1 ML/year. The annual load of total
suspended solids from the existing site (the caravan park) was predicted to be
©2012 Simmonds & Bristow Pty Ltd Contrast Constructions J-1005-310 - 13 January 2012
I \CLIENTFILES\Contrast Cons1rudions11 108-155c - Essence of Peregian SCEP Stage 1 Update109_Output Documents\1 108.155C_SWMP
SCEMP_Scanlon Property Group_V3 0_ta_120113 doc Page 10 of 24
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
PART Response to Information RequestRelated documentApplication case desk ↗
About this file
- File size
- 26.7 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.