4. ASSESSMENT MANAGER CONDITIONS
MATERIAL CHANGE OF USE
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Currency Period
2. This development approval lapses if the use has not happened by 27 July 2029, unless an
application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the tables below. The plans must be amended to incorporate
the amendments listed within the table below and resubmitted to Council prior to the issue
of any Development Permit for Building Works*.
Plan No. Rev. Plan/Document Name Date
C1.0 - Basement Floor Plan, prepared by Chris 07.09.2023
Clout Design
C1.1 - Ground Floor Plan, prepared by Chris Clout 07.09.2023
Design
C1.2 - Upper Floor Plan, prepared by Chris Clout 07.09.2023
Design
C1.3 - Roof Plan, prepared by Chris Clout Design 07.09.2023
C2.0 - Elevations, prepared by Chris Clout Design 07.09.2023
C3.0 - Sections, prepared by Chris Clout Design 07.09.2023
C3.1 - Sections, prepared by Chris Clout Design 07.09.2023
Building Height
4. The maximum height of the development must not exceed 8 metres above the natural ground
level and the exposed portion of the external façade of the building, except for the apex of
the roof of the units which must not exceed 8.535 metres.
5. The ground around the basement level is to be backfilled to ensure no part of the basement
is above finished ground level.
6. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld) which
certifies that the buildings do not exceed the maximum height requirement of this Decision
Notice.
Performance Bond
7. Security in the form of a cash bond or trading bank guarantee to the sum of $40,000 must
be submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
will be returned on performance of the conditions of approval less any costs incurred by
Council in respect of enforcing performance of this permit. Council reserves the right to call
upon the bond or guaranteed sum to effect compliance with conditions.
Page 2 of 15
Document Set ID: 22622601
Version: 3, Version Date: 17/10/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Negotiated Decision Notice - MCU22 0196 & OPW22 0295 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 172 KB (small file)
- File type
No other editions are linked here.