                                                                         Workplace Management Plan
                                                                      Lake MacDonald Drive, Cooroy

The ESCP is designed in compliance with,

▪    Best Practice Erosion and Sediment Control (IECA, 2008)
▪    State Planning Policy (DILGP, 2017)
▪    Appendix B – draft (IECA, 2018)
▪    Complying with the SPP – Technical Note for Government Development Assessment Compliance Officers
     (Healthy Land and Water, 2018)


Shadforth aim to minimise the movement of soil from its source, and sediment release outside the construction
site. This project has the potential to cause soil erosion, sediment loss, and sediment deposition which may
impact the surrounding environment and waterways.

An ESC plan is developed by the Environmental Advisor, CPESC Consultant, or the client prior to construction
commencing. The plan details the necessary ESC methods required on this project. ESC methods applicable
to this project are outlined in Table 9.
Table 9 – ESC Control Methods

             ESC Method                                                         Function
                                          ▪ Contain water on site until it can be treated and tested to ensure
    Sediment Basins                         compliance with water quality parameters.
                                          ▪ Control discharge of contaminated water.
                                          ▪ Isolate existing clean water flows through site.
    Clean Water Drain
                                          ▪ Prevent clean water from entering the site.

    Dirty Water Drains                    ▪ Capture site water and direct to sediment basin.

    Shaker Grid / Wheel Bath              ▪ Minimise sediments leaving site on vehicles.

                                          ▪ Prevent erosion.
    Sediment Fence
                                          ▪ Minimise sediment deposition in surrounding environment.

                                          ▪ Used in water bodies to minimise the movement and flow of
    Sediment Curtain
                                            sediments.
                                          ▪ Surface stabilisation
    Geofabric
                                          ▪ Dust minimisation.
                                          ▪ Surface stabilisation
    Hydro mulch / Mulch
                                          ▪ Dust Minimisation.
                                          ▪ Surface stabilisation
    Soil Polymers
                                          ▪ Dust minimisation.
    Rock Checks                           ▪ Reduce flow rate in drains and waterways to minimise scour.

    Straw Bales / Coir logs               ▪ Reduce flow rate in drains and waterways to minimise scour.
    Rock                                  ▪ Prevents scouring by protecting surfaces.

                                          ▪ Prevents erosion and sedimentation through surface permanent
                                            stabilisation.
    Landscaping & Vegetation
                                          ▪ Prevents dust.
                                          ▪ Provides aesthetically pleasing finish to construction works.



IMS-04-01_P – Reviewed – September 2020        Document Uncontrolled When Printed                           Page 37 of 60
Log in to download the original file

Lake MacDonald Drive Cooroy - WMP.pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.