Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
The Foreman shall perform the following pre-commencement checks:
• Check that the set out for Subgrade trim is adequate;
• Brief the work crew on the extent of the work, making note of the survey system in place.
The Foreman shall not proceed with placing pavement materials until a survey check has been completed to
confirm that the embankment has been trimmed within tolerance.
The Foreman shall verify material placement techniques and arrange for testing of pavement materials as
required by the specifications.
Pavement Construction
If required, the Project Manager shall gain approval of material to be used as Pavement Material.
The Foreman shall perform the following pre-commencement checks:
• Confirm the preparatory works are complete
• Confirm that the set out is adequate;
• Brief the work crew on the extent of the work.
Pavement material shall be placed in accordance with the specification.
The Foreman shall verify material placement techniques and arrange for testing of pavement materials as
required by the specifications.
The pavement construction will be performed in accordance with good industry practice.
The Foreman shall either arrange a survey pick up of the pavement or use string lines and levels to confirm that
it has been trimmed to the tolerances as per specifications.
Stabilised Pavement
The Foreman shall provide daily production records, to the Principle, which detail:
• Hours worked
• Production rate
• Lot details
• Road name
• Chainage
Methodology for Stabilised Pavement
• Identify location:
• Lot description
• Chainage
• Area (m)
• Pulverise area to the required depth as per specifications or instructions
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 44 of 60