                                                                       Workplace Management Plan
                                                                    Lake MacDonald Drive, Cooroy

Bitumen Surfacing

The Project Manager shall gain the following approvals prior to commencement:

▪    Verify that the subcontractors method and equipment has been approved by the Superintendent;

▪    Obtain from the subcontractor certificates verifying that aggregate and bitumen products comply with the
     specification

The Foreman shall perform the following pre-commencement checks:

▪    Ensure that surface preparation is in accordance with the specification;

▪    Ensure that road furniture is protected;

▪    Brief the subcontractor’s crew on the extent of the work;

Bitumen surfacing will be placed in accordance with the specification.

Tests will be taken in accordance with the specification.

Subcontract’s quality records will be collated for each scope of works, and submitted to the Superintendent for
approval.

Asphalt Pavements

The Project Manager shall gain the following approvals prior to commencement:

▪    Verify that the subcontractor’s method and equipment has been approved by the Superintendent;

▪    Obtain from the subcontractor certificates verifying that aggregate and bitumen products comply with the
     specification.

The Foreman shall perform the following pre-commencement checks:

▪    Ensure that surface preparation is in accordance with the specification;

▪    Ensure that road furniture is protected

▪    Brief the subcontractor’s crew on the extent of the work.

Tack coating will be applied in accordance with the specification.

Asphalt will be laid and compacted in accordance with the specification.

Tests will be taken in accordance with the specification.

Subcontractor’s quality records will be collated for each scope of works.

Excavation, Installation & Backfill of Culverts

The Foreman shall perform the following checks before excavation and preparation of foundation commences:

▪    Confirm that the set out is adequate;

▪    Confirm that an excavation permit is in place;

▪    Confirm the location of existing services;

▪    Ensure that the equipment is appropriate for the required task;




IMS-04-01_P – Reviewed – September 2020      Document Uncontrolled When Printed                      Page 46 of 60
Log in to download the original file

Lake MacDonald Drive Cooroy - WMP.pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.