Lake MacDonald Drive Cooroy - WMP

of 61

Page text shows just the words. Original shows the document exactly as it was published.

                                                                       Workplace Management Plan
                                                                    Lake MacDonald Drive, Cooroy

▪ Verify that the subcontractors method and equipment has been approved by the Superintendent/

The Foreman shall perform the following pre-commencement checks:

▪    Ensure that surface preparation is in accordance with the specification;

▪    Verify that the topsoil is of high quality and capable of supporting plant growth;

▪    Brief the subcontractor’s crew on the extent of the work.

Topsoil will be placed in accordance with the specification.

Fertiliser and planting/seeding will be applied at the rates outlined in the specification.

The planted/seeded area will be watered at the frequencies outlined in the specification.

Fencing

The Project Manager shall gain approval of the fencing subcontractor.

The Foreman shall perform the following pre-commencement checks:

▪    Confirm that the set out is adequate;

▪    Confirm that an excavation permit is in place;

▪    Confirm the location of existing services;

▪    Ensure that the equipment is appropriate for the required task;

▪    Brief the fencing subcontractor on the extent of the work.

The fencing shall be performed by a competent fencer in accordance with the drawings and specification.

Installation of Rock Protection

The Project Manager shall gain the following approval:

▪    Approval of the rock source.

▪    Ensure cages and wire has been manufactured in accordance with the drawings and specification.

The Foreman shall perform the following pre-commencement checks:

▪    Ensure geofabric has been stored in accordance with the manufacturer’s recommendations;

▪    Ensure equipment is suitable for the required task;

▪    Brief the work crew on the extent of the work.

The Foreman shall ensure that geofabric has been installed in accordance with the drawings, specification and
manufacturer’s recommendations.

Rock protection shall be installed in accordance with the drawings and specification.

Where indicated on the drawings, containment concrete shall be placed over the top of the rock protection.

Grouting

The Project Manager shall perform the following checks:




IMS-04-01_P – Reviewed – September 2020      Document Uncontrolled When Printed                     Page 50 of 60
Log in to download the original file

Lake MacDonald Drive Cooroy - WMP.pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.