Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
▪ Gain approval of the Grout Product from the Superintendent;
The Foreman shall perform the following checks before grouting commences:
▪ Ensure that base plate reservations have been thoroughly cleaned;
▪ Confirm that base plate reservations have been soaked for a minimum of 24 hours;
▪ Ensure that an MSDS is available for the grout product in use and that all safety precautions have been
implemented.
Grout will be prepared, mixed and installed in accordance with the manufacturer’s recommendations.
Backfill to Structures
The Foreman shall perform the following pre-commencement checks:
▪ Ensure concrete has been cured in accordance with the specification;
▪ Ensure backfill material is free from organisation matter and suitable for use;
▪ Ensure equipment is suitable for the required task;
▪ Brief the work crew on the extent of the work.
Structures shall be backfilled in accordance with the drawings, taking care to bring material up all sides of the
structure in a uniform manner.
The Foreman shall ensure that compaction tests are taken at the frequency defined in the specifications.
Once pre-commencement checks have been performed, it is Shadforth Foreman’s responsibility to ensure that
works are constructed in line with project drawings and specifications, and that survey and testing is carried out
throughout construction. It is the Project Manager’s responsibility to verify the correct completion of works, and
ensure that all required testing and survey has been conducted and documented for handover to the client.
Vehicle Management Plans (Site Specific) - The establishment of site specific Vehicle Management plans
(VMP’s) will address issues relating to:
▪ Parking onsite.
▪ Traffic flow on site.
▪ Pickup and delivery to site.
▪ Set down areas.
▪ Removal of waste from site.
▪ Essential services provided to the site
▪ Storage of plant not in use
▪ Traffic movement around/near the site
The VMP will be implemented in accordance with the Vehicle Management Plan Procedure IMS-02-30. VMP’s
will be constructed through consultation and communication with the Project Engineers, Supervisors and
workers. The VMP must be communicated to workers as part of the induction process. The VMP may be
amended where any change to the site dictates the necessity for a change. Where the VMP has been amended,
it must be communicated to the workers through pre-starts and Tool box talks.
Equipment – A register will be provided in the PCP that will evidence equipment on site, is in calibration and/or
properly test and tagged as per statutory requirements. This includes but not limited to, safety equipment e.g.
chains, slings, electrical, gas detectors, fire extinguishers, monitoring equipment, harnesses, tripods etc through
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 51 of 60