Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
3. MANAGEMENT SYSTEM ACCREDITATION
Shadforth have a 3rd party accredited Integrated Management System (IMS) which meets the requirements of
the below standards;
▪ AS/NZS ISO 9001 Quality Management Systems
▪ AS/NZS 4801:2001 Occupational Health & Safety Management Systems
▪ AS/NZS ISO14001 Environmental Management Systems
▪ Federal Safety Commission Audit Criteria Guidelines 2015
▪ Work Health & Safety Act 2011
▪ Work Health & Safety Regulation 2011
▪ Environmental Protection Act 1994
▪ Any associated Australian standards applicable to the civil construction industry
▪ Any associated codes of practice applicable to the civil construction industry
A copy of the accreditation certification can be provided upon request.
4. POLICIES
Compliance policies have been developed as a statement of commitment from Senior Management and reflect
the values and ethos of the organisation. Business objectives and intentions are outlined in the Quality, Safety,
Environmental and Rehabilitation Policies that are implemented on Shadforth Sites.
All company policies, procedures and plans are reviewed annually and recorded in the company’s document
control system in a controlled Register IMS-06-03.
5. OBJECTIVES & TARGETS
Objectives and targets for this project, have been set out by the Senior Management Team. These objectives
and targets are consistent with the company policies outlined in section 4.
Senior Management Commitment to;
▪ Ensuring resources are allocated to implement the Workplace Management Plan to conform to the
requirements of AS/NZS ISO 9001 Quality Management System Requirements, AS/NZS 4801:2001
Occupational Health & Safety Management Systems, and AS/NZS ISO 14001 Environmental Management
Systems on the project
▪ Ensuring products and services provided on the project meet or exceed the quality standards prescribed in
the contract agreement
▪ Ensuring the HIRAC process is conducted at all levels of the business to reduce hazards and risks in line
with section 5 & 13 of the IMS Manual.
▪ No Loss Time Injuries (LTI) on the project
▪ Ensuring all incidents classified as Moderate, Major or Catastrophic and/or as advised by the Compliance
Manager are investigated and preventative and corrective measures are implemented resulting from the
incident
▪ Ensuring project operating practices seek to minimise environmental impacts, prevent pollution, and
minimise the likelihood of environmental harm through best management practices.
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 5 of 60