Lake MacDonald Drive Cooroy - WMP
Workplace Management Plan
Lake MacDonald Drive, Cooroy
Table 1 - Compliance Observation and Documentation Timeframes
Reporting Position to Frequency
Description of Documentation / Records
Required Complete Required
Complete a Project Compliance audit IMS-05-76 through
Iauditor software. To be conducted with worker /
subcontractor involvement.
Compliance Attach a rectification action plan IMS-05-69 for items
Project Audits Quarterly
Advisor identified as non-compliant.
The items on the RAP are required to be rectified in the
documented timeframe and signed off as completed and
sent to compliance.
Senior Management Observation IMS-05-77 through
Management Senior
Monthly Iauditor Observation report to be completed with
Observations Management
management / worker / subcontractor involvement.
WHSE advisor or Complete a project inspection with worker/subcontractor
Project
Site Foreman or Monthly involvement. To be completed using Project Compliance
Inspections
Project Manager Inspection IMS-05-79.
Within a Complete a Subcontractor Spot Check using document
WHSE Advisor or
Subcontractor week of Subcontractor Spot Checklist IMS-05-48 with the
Spot Checks Site Foreman or Starting or subcontractor involvement.
Project Manager as required Spot check to be kept in the PCP folder onsite
Regional
Construction
Manager or
Project Manager Complete a Toolbox Talk Form IMS-05-52, ensuring all
or Site Foreman attendees sign the attendance record.
Tool Box Talks or WHSE Advisor Weekly
or Workers / TBT to be kept in the PCP folder onsite and copy sent to
guests with compliance
relevant WHS and
/ or site
information.
Compliance
System Audit manager Annually Compliance System Audit Form IMS-05-04
System controller
IMS-04-01_P – Reviewed – September 2020 Document Uncontrolled When Printed Page 6 of 60