Appendix F - Construction Management Plan

of 4

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
          CONSTRUCTION MANAGEMENT PLAN




PROJECT DETAILS

Location: 157 Lawnville Road Black Mountain 4563 QLD

Site Contact: Matthew McGee

Contact number: 0409 592 224.
Log in to download the original file

Appendix F - Construction Management Plan.pdf · 4.1 MB (large file)

The download may take up to a minute.

Full text of the other 3 pages

Page 2

CONSTRUCTION WORKS

Staging of project:

Stage 1. construction of Cabin 1 and 2

Stage 2. construction of Cabin 3 and 4 to commence about 24 months after completion of stage 1

Estimated construction time for stage 1. 20 weeks



DEMOLITION

No demolition is required to carry out project.



EXCAVATION

Excavation works will consist of bore holes for footings no cut and fill required.

Cabins are constructed on stumps above ground to minimise disturbance.

Minimal excavation required for sewer tank and associated plumbing.

Trenching for power is through open paddock so as not to disturb vegetated areas.



CONSTRUCTION

Cabins will be timber frame construction on steel posts, cladding to be Australian hardwood natural
finish to blend with environment. Roofing material colour bond steel.

Access drive and turning circle gravel.



NOISE MITIGATION

•   Construction hours 6.30 am and 5.30 pm Monday to Saturday. No construction Sundays.
•   Consultation with neighbours.
•   Selection of quieter equipment where possible.
•   Performance of regular maintenance on equipment.



STORMWATER AND SEDIMENT CONTROL

•   Manage soil disturbance minimal excavation works to reduce sediment.
•   Sediment control fencing to be placed is appropriate locations.
•   Trenches backfilled in a reasonable time, Trenches not to be left open for prolonged periods.
•   Weather dependant, excavation and trenching to not take place before know weather event .

Page 3

BUILDING WASTE

•   Waste materials to be contained in a bin or enclosure prior to removal from site.
•   Materials to be covered or weighed down to prevent wind spreading materials over site and
    waterway.

TRAFFIC MANAGEMENT

•   Minimise truck movements with good planning bulk material deliveries.
•   No removal of soil required from site.
•   On site parking for trades
•   Spotter for trucks moving on and off site.

TREES AND VEGITATION

•   Cabins located in clearings to avoid Tree and vegetation disturbance.
•   Access driveways at fence line located in areas to create minimal disturbance.

Page 4

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.