Appendix F - Construction Management Plan
Plans and drawings: the text below has words only, no drawings.
CONSTRUCTION WORKS Staging of project: Stage 1. construction of Cabin 1 and 2 Stage 2. construction of Cabin 3 and 4 to commence about 24 months after completion of stage 1 Estimated construction time for stage 1. 20 weeks DEMOLITION No demolition is required to carry out project. EXCAVATION Excavation works will consist of bore holes for footings no cut and fill required. Cabins are constructed on stumps above ground to minimise disturbance. Minimal excavation required for sewer tank and associated plumbing. Trenching for power is through open paddock so as not to disturb vegetated areas. CONSTRUCTION Cabins will be timber frame construction on steel posts, cladding to be Australian hardwood natural finish to blend with environment. Roofing material colour bond steel. Access drive and turning circle gravel. NOISE MITIGATION • Construction hours 6.30 am and 5.30 pm Monday to Saturday. No construction Sundays. • Consultation with neighbours. • Selection of quieter equipment where possible. • Performance of regular maintenance on equipment. STORMWATER AND SEDIMENT CONTROL • Manage soil disturbance minimal excavation works to reduce sediment. • Sediment control fencing to be placed is appropriate locations. • Trenches backfilled in a reasonable time, Trenches not to be left open for prolonged periods. • Weather dependant, excavation and trenching to not take place before know weather event .
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.