Cover Letter information Reponse - Auxilium Consulting
29 May 2026
Mr M Pinese
Planning and Development
Noosa Council
PO Box 141
Tewantin, Qld 4565
Dear Mr Pinese,
Re: RAL 26/0001 Information Request
At: 25 Tulip St, Cooroy
With reference to the abovementioned development application and the Information Request from
Council dated 7 April 2026, we have prepared a response to the engineering matters raised as
follows:
Items 1-3. Legal Point of Discharge, location and sizing of Detention Tanks
The Stormwater Management Plan and modelling have been updated to address these items. An
assessment of the LPOD criteria utilising QUDM has been undertaken with the outcomes
incorporated into the development’s proposed stormwater management. This identified that no
actionable nuisance is occurring as there is no increase in stormwater quantities and/or velocities
that may arise in third-party damage. Interception and detention of generated flows and discharge
via a level spreader device ensures that no concentration of flows is occurring at the naturally
formed drainage channel existing throughout the greater catchment.
Item4. Assessment of RAL Code
Assessment of PO12 of the RAL Code is detailed below:
Performance Outcome Acceptable Outcomes
PO12 AO12.1
New lots are located, sized and configured so All lots are connected to power supply and
as to ensure each lot is capable of being telecommunications services and where located within the
serviced by appropriate levels of infrastructure Urban boundaries, power supply and communications
including: infrastructure are provided underground.
a. power supply;
b. telecommunications; and Complies – the development is readily accessible to
c. where within Local Plan Areas connection to such reticulation and can be reasonably
d. reticulated water supply; conditioned to comply.
e. reticulated sewerage; and
f. stormwater drainage.
AO12.2
Auxilium Consulting Pty Ltd
ABN 84 639 195 092
Bli Bli, Qld 4560
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Cover Letter information Reponse - Auxilium Consulting.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 1 page
Page 2
If located in a water service area each new lot can be
connected to Unitywater’s water supply network.
Complies – the development is readily accessible to
connection to such reticulation and can be reasonably
conditioned to comply.
AO12.3
If located in a sewerage service area each new lot can be
connected to Unitywater’s sewerage network.
Complies – the development is readily accessible to
connection to such reticulation and can be reasonably
conditioned to comply.
AO12.4
If located in a Local plan area lots can be connected to
Council’s stormwater drainage network.
Generally complies – the proposed development cannot
achieve connection to the stormwater network via
gravity due to the terrain and its position below the
road’s kerb and channel. An acceptable outcome is
achieved by assessing against the LPOD criteria in QUDM
which determines that no actionable nuisance occurs if
the stormwater quantities and/or velocities do not cause
third-party damage. Therefore, utilising on site detention
strategies and a level spreader device to the LPOD,
compliance with QUDM and this PO is achieved.
AO12.5
If not in a sewerage service area each lot has sufficient
area and other attributes to ensure efficient and effective
on-site sewerage disposal.
Not applicable
We believe that the above satisfactorily addresses the engineering matters raised however, should
additional information be required, please contact our office directly.
Yours sincerely,
Jaro Bauleka
Senior Engineer (Civil)
Encl
1. Stormwater Management Report
Auxilium Consulting Pty Ltd
ABN 84 639 195 092
Bli Bli, Qld 4560