Town Planning Report and Appendices - Cooroibah
Attached to the e-mail Development Permit – 23 Jirrima Crescent, Cooroibah MCU16/0099.
The original of this document is very large (14.9 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
for a number of referral agency triggers now that the SARA provisions have
commenced, there are still a number of other entities that exist outside of SARA,
that still hold jurisdiction for their own referral agency triggers.
In accordance with Schedule 7 of the Sustainable Planning Regulation 2009 (SP
Reg), the proposed development requires referral for the following matters:
Constructing or raising waterway barrier works
The proposal will require referral to DILGP who will act as a ‘concurrence agency’
in accordance with Sustainable Planning Regulation 2009 – Schedule 7, Table 2,
Item 29, as the proposal involves the replacement of the existing culvert in a
Type 1 – Low waterway. The proposed works are not considered to constitute
Self Assessable development as the removal of vegetation lower than ground will
likely be required.
State Development Assessment Provisions
The Queensland State Development Assessment Provisions (SDAP) set out the
matters of interest to the State for development assessment, where the Chief
Executive administering SPA (that, is the Director-General of DSD), is
responsible for assessing development applications as either Assessment
Manager or Referral Agency.
The SDAP is prescribed as a statutory instrument under SPA and contains the
matters the Chief Executive of SPA may have regard to in development
assessment, bounded by the decision-making rules outlined in SPA.
Specifically, the SDAP states that where the Chief Executive is a Referral Agency
for a development application under the provisions of the SP Reg mentioned in
Table B.3, Column 3, the application must comply with the State codes
mentioned in Table B.3, Column 5.
Table 4 summarises the relevant provisions of the SP Regulation (that is, the
referral triggers identified in Table 1) together with the matters of interest and
relevant SDAP module and corresponding code. Appendix F – SDAP Code
Assessment includes an assessment of the proposed works against each
module.
Table 4 - State Development Assessment Provisions Codes relevant to proposed
development
Matter of State Relevant Provision of Prescribed Relevant Module & Code
Interest the Regulation (for Material Change of Use)
Constructing or Schedule 7, Table 2, Module 5: Fisheries Resources
raising waterway Item 29 5.2 Constructing or raising waterway
barrier works
Page 36
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.