Skip to the record
Noosa's #1 Council Tracker.

Council archive · source document

2017-06-06 - P&E Agenda Attachment 1 to Item 6 Draft Alignment Amendments Part 1 (Pages 1-907)

of 907

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (18.9 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Table Error! No text of specified style in document.-24 — For All Residential Uses




                                                                                                                                    Including amendments to 3 July 2017
                         column 1                                                    column 2




                                                                                                                        The Noosa Plan
                     Specific Outcomes                              Probable solutions (if code assessablecode
                                                                                   assessment)
14.46         Effects of use
Electricity supply infrastructure
O1 The development does not adversely                              S1.1 No solution provided
impact on existing or future electricity supply
infrastructure;
AND
O2 All uses and works maintain an adequate                         S2.1 Development for uses adjacent to or
safe distance from electrical infrastructure                       within 50m of an existing electricity substation
including substations, overhead powerlines,                        incorporates noise attenuation measures to
power poles and transformers.                                      mitigate noise impacts;
                                                                   AND
                                                                   S2.2 Buildings and structures (including
                                                                   swimming pools, sheds, tennis courts or
                                                                   outbuildings) are not constructed under
                                                                   overhead electricity transmission lines, or
                                                                   within electricity easements;
                                                                   AND
                                                                   S2.3 A minimum separation distance is
                                                                   maintained from the electricity transmission
                                                                   line to the closest boundary of habitable
                                                                   buildings and child activity areas, as follows—
                                                                   a)     20m for transmission lines up to 132kV;
                                                                   b)     30m for transmission lines between
                                                                          133kV and 275kV; and
                                                                   c)     40m for transmission lines greater than
                                                                          275kV.
Water supply and conservation                                                                           18
                                                                   S3.1 & S4.1 For a Class 1 building other than
O3 On-site water storage is designed and
                                                                   a Detached house , outside a reticulated
operated to support the efficient use of water;
                                                                   water service area, a rainwater tank is to be
                                                                   installed with the following minimum storage
AND
                                                                   capacities—
O4 On-site water storage is adequate for                                  a) Where no more than 3 bedrooms –
occupants every day use and fire fighting                                     45,000 litres; or
purposes.                                                                 b) Where more than 3 bedrooms –
                                                                              60,000 litres;
                                                                   AND
                                                                          c) There is to be on the lot a dam,
                                                                              swimming pool or water tank
                                                                              accessible for use by the fire brigade
                                                                              that contains at least 5,000 litres of
                                                                              water.

                                                                   Editor’s note:
                                                                   The 5,000 litres required can be included
                                                                   within the water required in S3.1 or S4.1
                                                                   providing it is accessible for the purpose of fire
                                                                   fighting at all times and not used for other
                                                                   domestic purposes.

                                                                   Advisory note

18
     Class 1 Buildings are defined under the Building Code of Australia



                                                               47
                                                     Residential Uses Code

Used in these records

About this file

File size
18.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2017-06-06 - P&E Agenda Attachment 1 to Item 6 Draft Alignment Amendments Part 1 (Pages 1-907)(PDF, 18MB).pdf · 18.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.