Table 14-42 — All Demolition, removal or relocation




                                                                                                                         Including amendments to 3 July 2017
                    column 1                                              column 2




                                                                                                             The Noosa Plan
                Specific Outcomes                               Acceptable solutions (if self-
                                                         assessableaccepted development subject to
                                                                       requirements)
                                                         Probable solutions (if code assessablecode
                                                                        assessment)
14.85      Re-use of buildings or materials
O1 Opportunities for re-use of buildings are             S1.1 Buildings are relocated to another site and
maximised.                                               adapted to meet the needs of users.
                                                         OR
                                                         S1.2 At least 10% of building materials are
                                                         reused or recycled (measured in cubic metres).
O2      The development ensures waste during             S2.1 For assessable development a Waste
any construction and demolition works is                 Management Plan prepared in accordance with
minimised and construction and demolition                Schedule 8 Demolition & Construction Waste
materials are reused and recycled where                  Management specifies—
possible.                                                a)   estimated volumes of waste to be
                                                              generated;
                                                         b)   estimated volumes of recyclables;
                                                         c)   initiatives to minimise waste by waste
                                                              reduction, reuse or recycling;
                                                         d)   plans showing the location and details of
                                                              the waste storage areas; and
                                                         e)   a description of the type of containers
                                                              proposed to store the waste.

14.86      Safety and protection of infrastructure
O3 Demolition, removal, relocation or                    S3.1 Infrastructure including, reticulated water,
associated works does not result in—                     sewerage, stormwater, and electricity are
a)   ‘live’ or ‘active’ infrastructure that may          protected from damage and made safe to the
     present a risk to people using the site or          standard required by the regulatory authority;
     surrounding areas; or                               AND
b)   damage to infrastructure or other works.            S3.2 Infrastructure is disconnected, capped or
                                                         sealed including--
                                                         a)     electricity meters are removed and
                                                                electrical wires disconnected; and
Editor’s note:                                           b)     telephone lines are disconnected; and
An approval will be required from Council’s Building     c)     high speed data cables and television
and Plumbing Services for decommissioning                       provider boxes are disconnected and
plumbing apparatus including–                                   removed;
     sanitary drains or reticulated water supply; and
                                                         AND
     septic tanks, holding tanks or on-site treatment
          systems.
                                                         S3.3 A temporary crossing is provided to
                                                         protect road reserve infrastructure including
                                                         kerb and channel;
                                                         AND
Advisory note:
                                                         S3.4 Any damage to footpaths, street
An approval will be required from Council’s
                                                         plantings, natural vegetation/trees kerb and
Plumbing Section for decommissioning plumbing            channel, bridges or roadways at the removal
apparatus including–                                     site, the new site or between the sites is
 sanitary drains or reticulated water supply; and       repaired or reinstated to at least pre-existing
 septic tanks, holding tanks or on-site                 conditions.
   treatment systems.
14.87      Amenity and environmental protection
O4 Waste materials are removed from the site             S4.1 Waste materials are removed from the
to avoid causing unhealthy conditions                    site.


                                                       97
                                      Building Removal and Demolition Code

Used in these records

About this file

File size
18.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2017-06-06 - P&E Agenda Attachment 1 to Item 6 Draft Alignment Amendments Part 1 (Pages 1-907)(PDF, 18MB).pdf · 18.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.