                              13.2.5.    Headworks shall be calculated as the value of headworks assessed at the
                                         time prescribed by the Local Government (Planning and Environment) Act
                                         1990, plus interest charged at the rate set by the Queensland Treasury
                                         Corporation for Local Government borrowings as they apply to Noosa
                                         Shire. The interstate used shall be the rate current at the “time prescribed”
                                         above;
                              13.2.6.   Should the contributions not be paid at the due time, Council shall call upon
                                        the security Lodged; and
                              13.2.7.   in the case of a building permit, if a permit expires the securities held will be
                                        returned.
               14.    The developer shall bear the cost of alteration of any public utility or other facilities
                      necessitated by the developer of the land or associated construction works external to the
                      site.
               15.    Connection to Council’s existing water supply and sewerage reticulation systems at the
                      developer’s expense to the standards and requirements of Council’s Shire Engineer.
               16.    Submission of two sets of professionally drawn scale plans in compliance with Council’s
                      Code controlling food establishments for approval by Council’s Health Surveyor, for any food
                      premises proposed to be included in development. Approval is to be obtained prior to fitting
                      out the building.
               17.    Provision of any imperviously paved and drained area to be drained to Council’s to sewer to
                      accommodate all refuse containers to the reasonable satisfaction of Council’s Health
                      Surveyor. This area is to be aesthetically screened from any road frontage or adjoining
                      property boundary and is to be setback a distance of two (2) metres from any road frontage.
                      A suitable hosecock and hose are to be located in the vicinity of the refuse container area.
               18.    Provision of separate toilet facilities for patrons, in addition to staff toilet facilities, in
                      accordance with Council’s Policy of 16th October, 1985.
               19.    The footpath and setback areas are to be kept clear of goods, signs and street furniture not
                      approved by Council.
               20.    Submission of a cash bond or trading bank guarantee to the sum of $3,000.00 secure
                      performance of conditions, prior to the issue of a Building Approval. The cash bond or trading
                      bank guarantee will be returned upon performance of the conditions of approval.
               21.    The provisions of this approval are to be effected, prior to the commencement of the
                      approved use. Council reserves the right to call upon the bond or guaranteed sum referred
                      to in this approval to effect compliance with conditions.
               22.    The Town Planning Consent Permit may be revoked pursuant to section 4.14 pf the Local
                      Government (Planning and Environment) Act if commencement of erection or works have
                      not been made in accordance with that Permit or the rights conferred by that Permit are not
                      exercised within two (2) years of the date of issue of the permit.
               23.    The Town Planning Consent Permit lapses where:-
                      23.1. the use or erection of a building or other structure associated with the use, has not
                            been commenced within four (4) years of the date of issue of the Town Planning
                            Consent Permit, unless application is made and approved by Council for an extension;
                            or
                      23.2. the use of any premises pursuant to the Town Planning Consent Permit ceases for a
                            period of twelve (12) months.
               5.     REFERRAL AGENCIES

               Not applicable.




                                                                                                           Page 4 of 7
Document Set ID: 23993968
Version: 4, Version Date: 05/08/2025

Used in these records

About this file

File size
166 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - 51995 1645 01 (As Published).pdf · 166 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.