Minor Change Report MCU25 0057 01, OPW25/0078.01 & RAL25/0010.01 [As Published]
a. a. a driveway crossover in accordance with Council’s standard drawings RS-049, RS-
050 and any associated addendum.
Furthermore, a condition number needs to be added to the car parking condition, as follows:
Car Parking
27. A minimum of 4 car parking spaces must be provided and marked on the site and generally
in accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) dated March 2519/06/2026 and must include in particular:
a. a. dimensions, crossfalls and gradients in accordance with Australian Standard
AS2890: Parking Facilities
Existing Condition 27
Pedestrian Facilities
27. Construct a 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to George Street.
Condition 26 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Recommended Correction of Administrative Matters
It is recommended that this condition be updated, as follows, to refer to the correct condition
number in the second sentence as the condition is numbered:
28. Construct a 1.5 metre wide footpath within the road verge for the entire length of the site’s
frontage to George Street.
Condition 2628 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Existing Condition 28
Stormwater
29. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with SCG Consulting
Engineer’s Operational Works Stormwater Management Plan (00469-SW1.1) dated March
25 and must include in particular:
a. 3,000L of on-site rainwater retention per dwelling.
Condition 27 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Recommended Correction of Administrative Matters
It is recommended that this condition be updated, as follows, to refer to the correct condition
number in the second sentence as the condition is numbered and to reference the updated
Stormwater Management Plan:
Stormwater
28. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken generally in accordance with SCG Consulting
Engineer’s Operational Works Stormwater Management Plan (00469-SW1.1) dated March
2519 June 2026 and must include in particular:
a. 3,000L of on-site rainwater retention per dwelling.
Condition 2728 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Page 16 of 20
Document Set ID: 24926353
Version: 9, Version Date: 10/08/2026