Minor Change Report MCU25 0057 01, OPW25/0078.01 & RAL25/0010.01 [As Published]
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below.
Plan No. Rev. Plan/Document Name Date
01 - Subdivision Plan prepared by JL 12/05/2025
20/19 4 Subdivision Plan prepared by Metricon 20/03/2026
Assessment of Request
The submitted Subdivision Plan is in accordance with the changes endorsed in this application and
as such it is agreed it can replace the previously approved Subdivision Plan.
Recommendation
It is recommended existing condition 3 be amended to read as follows:
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table/s below.
Plan No. Rev. Plan/Document Name Date
01 - Subdivision Plan prepared by JL 12/05/2025
20/19 4 Subdivision Plan prepared by Metricon 20/03/2026
Administrative corrections relating to Conditions 26,27 and 28
Existing Condition 26
26. A sealed access driveway must be provided from George Street to all parking and
manoeuvring areas of the development. The works must be undertaken generally in
accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1) and Operational Works Driveway Details Plan (00469-OW4.2) dated March
25 and must include in particular:
a. a. a driveway crossover in accordance with Council’s standard drawings RS-049, RS-
050 and any associated addendum.
Car Parking
A minimum of 4 car parking spaces must be provided and marked on the site and generally in
accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan (00469-
OW4.1) dated March 25 and must include in particular:
a. dimensions, crossfalls and gradients in accordance with Australian Standard AS2890:
Parking Facilities
Recommended Correction of Administrative Matters
It is recommended that this condition be updated to reference the amended Driveway and Access
Plan, as follows:
26. A sealed access driveway must be provided from George Street to all parking and
manoeuvring areas of the development. The works must be undertaken generally in
accordance with SCG Consulting Engineer’s Operational Works Driveway & Access Plan
(00469-OW4.1, Rev C) dated March 2025 19/06/2026 and Operational Works Driveway
Details Plan (00469-OW4.2, Rev B) dated March 2025 19/06/2026 and must include in
particular:
Page 15 of 20
Document Set ID: 24926353
Version: 9, Version Date: 10/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.