Noosa Shire Council
Adopted Infrastructure Charges Resolution (No. 1) 2014
C. the claimant’s preferred tenderer;
D. the claimant’s reason for the preferred tenderer;
E. a copy of the proposed Work Contract issued by the
claimant’s preferred tenderer;
F. detailed plans and specifications showing the extent of
the Work Contribution eligible for an Infrastructure
Offset;
G. the claimant’s calculation of the cost providing a Works
Contribution to which an Infrastructure Offset applies;
H. the total of the claimant’s calculation of the Pre-Market
Estimate.
(4) The Council is to calculate the amount of the value of the infrastructure offset by
indexing the value of the infrastructure offset in accordance with the consumer
price index from the date of the notice given under section 11.3(2) (Claim for an
infrastructure offset) to the date that the infrastructure offset is to be offset against
an infrastructure charge.
11.5 Application of an infrastructure offset
The Council is to offset the amount of the value of an infrastructure offset against
an adopted infrastructure charge for the trunk infrastructure network to which the
trunk infrastructure contribution relates if the trunk infrastructure contribution is
supplied for the development by the claimant in accordance with the applicable
development approval and land dedication notice.
12. Refund of an unused infrastructure offset
12.1 Purpose
Section 12 states the Council’s policy for a refund of an unused infrastructure
offset for a trunk infrastructure contribution.
12.2 Application of section
Section 12 applies where:
(a) the development to which the trunk infrastructure contribution relates has
been lawfully completed;
(b) the trunk infrastructure contribution is planned under this document to
service the development of other premises (serviced premises);
(c) the amount of the value of an infrastructure offset has not been fully
offset against an adopted infrastructure charge for the trunk infrastructure
network to which the trunk infrastructure contribution relates under
Council Resolution dated 6 February 2014