ORDINARY MEETING AGENDA 18 NOVEMBER 2021
outside the lease area must be relocated to the designated storage area within the lease
area promptly by staff. Staff must regularly conduct an inspection of the foreshore areas
to ensure all vessels and associated equipment are stored in the designated storage
areas within the lease area.
10. Boat repair activities other than minor repairs such as replacing a battery are not
permitted within the lease area.
11. Wastewater and sullage must only be disposed of at approved pumpout facilities.
12. The building and associated landing must not be utilised for live-aboard purposes.
Currency Period
13. This development approval lapses if the use has not happened by 18 November 2027,
unless an application to extend the currency period is approved by Council.
Performance Bond
14. Security in the form of a cash bond or trading bank guarantee to the sum of $15,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to the issue of a Development Permit for Building Works. The cash bond or trading
bank guarantee will be returned on performance of the conditions of approval less any
costs incurred by Council in respect of enforcing performance of this permit. Council
reserves the right to call upon the bond or guaranteed sum to effect compliance with
conditions. The bond shall be released after 12 months from the date the use
commences. The applicant must notify Council in writing of the date the use
commences.
General Requirements
15. There must be no electrical reticulation system carrying electricity in excess of 24 volts
beyond the revetment wall unless all switches and power outlets are positioned above
the 1%AEP flood level.
16. Lighting associated with the use must be designed, installed, operated, and maintained
in accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor
Lighting.
17. Any construction and post construction activity must not impact on the condition of the
waterway, and must be conducted so as not to breach the Environmental Protection Act
EPA (1994) and the Environmental Protection (Water) Policy 2009.
18. After completion, the proposed works must be maintained in a sound state of repair in
accordance with the approved plans.
4 PLANNING APPLICATIONS DECIDED BY DELEGATED AUTHORITY – SEPTEMBER
2021
That Council note the report by the Development Assessment Manger to the Planning &
Environment Committee Meeting dated 9 November 2021 regarding planning applications that
have been decided by delegated authority.
Committee Recommendation
That the report of the Planning & Environment Committee dated 9 November 2021 be received and
the recommendations therein be adopted except where dealt with by separate resolution.
Page 7 of 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.