2014-11-20 Ordinary Meeting Minutes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ORDINARY MEETING MINUTES 20 NOVEMBER 2014
Staging & Sunset Clause for Completion
12. The development may be completed in stages, as shown on the approved
plans. Pursuant to s342 of the Sustainable Planning Act 2009, any
uncompleted aspects of this development approval lapse if the whole of the
approved use has not happened by 20 November 2020.
ENGINEERING
Site Access and Driveways
13. Concrete driveway and parking areas shall be provided generally in accordance
with Drawing Nos: OGSS-001-01, Rev G dated 18/09/2014 and OGSS-001-01,
Rev G dated 18/09/2014 – respectively titled: Site Plan Stage 2 and Stage 2
Basement Floor Plan, prepared by Steve McGregor Design Service and as may
be amended by the conditions of this permit. The works must be undertaken in
accordance with an engineering design prepared by suitably qualified
registered professional engineer and a Development Permit for Operational
Works, and shall include in particular:
A driveway crossover/s in accordance with IPWEAQ standard drawing SEQ R-
051 and to grades that prevent vehicles from scraping and/or bottoming.
For pedestrian safety between vehicles exiting the site and pedestrians on the
footpath, the driveway and any associated fencing or vegetation near the
driveway shall comply with the minimum sight line requirements as defined in
AS 2890.1, section 3.2.4.
All parking spaces, driveways and circulation lane in compliance with the
relevant sections of the current AS 2890.1 and AS2890.2.
Suitable safety measures, including: traffic directional signage, warning signage and
speed limit/s within the site, to improve driver awareness of pedestrians and enhance
pedestrian safety.
Provision of vandal resistant public lighting with intensities to satisfy the requirements
of Australian Standard AS1158: Public Lighting Code
14. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all
times.
Frontage Works - Footpath
15. Frontage works must be provided for the development. The works must be
undertaken in accordance with a Development Permit for Operational Works
and must include in particular:
a. A two (2) metre wide concrete footpath within the road verge for the entire
length of the site’s frontage to Rene Street in compliance with IPWEAQ
standard drawing SEQ R-065 Concrete Pathway Construction Details.
The footpath must match the levels the driveways to the site without step
or trip hazard. Where necessary existing driveway finish level should be
adjusted to ensure compliance grades for the footpath and driveway.
b. Replacement of any street trees affected by the frontage works.
Stormwater Drainage
16. Prior issue of building works approval for the new building on the eastern
portion of the site, an Operational Works approval for treatment of stormwater
quality must be obtained. The application for Operational Works Approval for
stormwater must provide for treatment of stormwater from the entire site.
Noosa Shire Council Page 14 of 19
This is not an official copy of Council’s Minutes
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.