Traffic Engineering Correspondence

Attached to the e-mail Response to Council information request - MCU16/0066 & OPW16/0133 - email 2 of 3.

of 34

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Pomona Connection Road allows for four years of existing Bruce Highway traffic, after which the road will
become a service road and the traffic volumes are expected to reduce significantly.

There was no traffic information available for Holts Road, Uhlmanns Road, Christies Road and
Woodswallow Lane and the DESA adopted for these roads were based on the minimum values
recommended in the SCRC Planning Scheme (SCRC, 2005), including estimated construction traffic
where applicable.
Some of the local roads and temporary pavements are expected to carry construction vehicles and the
estimated construction traffic has been allowed for in the pavement designs where applicable. The
estimated additional ESA’s as a result of the construction traffic are:
      Contract 1:         80,000 ESA’s (assumes 10,000 truck-and-dogs @ 8 ESA/HV)
      Contract 2:         700,000 ESA’s ((assumes 87,500 truck-and-dogs @ 8 ESA/HV)
The following temporary pavements, to allow for construction, have been included in the Detailed Design
Phase:
      Uhlmanns Road Extension
      Bruce Highway Side Track
      Side track at the Cooroy – Noosa exit ramp (southbound)
The pavement design traffic input parameters for these roads are summarised in Table 12.

Table 12           Design Equivalent Standard Axles (Temporary Roads)

    Road                             Design Life                     Opening Year                    DESA (ESA’s)
                                                                                                               1
    Uhlmanns Rd                      1 year                          2013                            100,000
    extension
                                                                                                                    2
    Bruce Highway Side               5 years                         2014                            14.7 million
    Track
                                                                                                               3
    Cooroy – Noosa exit              5 years                         2014                            300,000
    ramp
    Notes: 1. Includes Contract 1 construction traffic.
           2. Includes 3 years Bruce Highway and Contract 2 construction traffic.
           3. Based on existing southbound exit ramp traffic.




41/24401/11/437270       Bruce Highway (Cooroy to Curra) Upgrade Section A (Cooroy Southern Interchange - Sankeys Road)   13
                         Job No. 263/10A/12, Invitation No. NCHD-2454
                         Pavement Design Report
Log in to download the original file

Traffic Engineering Correspondence.pdf · 2.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.