Stormwater for domestic buildings
The roof of every domestic building shall be provided with a complete and effective
drainage system to the satisfaction of the building certifier, which must ultimately comply
with the requirements of the Building Code of Australia.
The stormwater drainage must discharge to the kerb and channel (road frontage) where
a kerb adaptor has been provided by the developer at the time of the original subdivision;
or if the minimum pipe grade of 1:100 is achievable and adequate cover over that pipe
can be obtained. In this instance, the pipe shall be connected to the kerbing with an
approved galvanized mild steel kerb adaptor. The kerbing shall be “neatly” cut so the
kerb adaptor can be grouted into position and once in position it does not change the
profile of the kerbing.
Where there is an inter-allotment drainage network provided with an approved
connection point to receive the property’s stormwater drainage system then it must
discharge to that drainage network.
If there is no inter-allotment drainage network and the private stormwater drainage
system falls away from the street it must be discharged to an on-site stormwater
dispersion system.
An on-site dispersion system (rubble pit) must be placed so that it does not cause
stormwater to pond under the floor of any building; or to flood around the foundations of
any building; or cause nuisance to neighbouring properties.
Document Set ID: 23245585 Page 1 of 2 October 09
Version: 1, Version Date: 16/09/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - Storm Water Management Plan 132001.210327.1Related documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.