Skip to the record
Every meeting, every word.

Council archive · source document

Approved Concept Environment Management Plan OPW11/0116.01

of 14

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
5. CONSTRUCTION

There are a number of ways in which these works could be achieved and the final methodology is at the discretion of the
contractor.

5.1 Equipment
Itis anticipated that the works (depending on the methodology) may require the use the following major equipment:

6” or greater cutter suction dredger and pipeline
Jet pump (suspended or hopper-fed)

Barge

Support vessels

Excavator

Bobcat

5.2 Methodology for Dredging / Nourishment

The dredge area is to be located accurately using DGPS or suitable altemative. Dredging is to be undertaken slowly to
minimise turbidity. Dredging is to be undertaken in such a way that it does not block navigation once a suitable channel is
established.

Nourishment is to be achieved generally by relocating the pipeline periodically within the deposition area. Small earthmoving
equipment may be used to redistribute material on the visible beach to achieve final nourished profiles. This may be more
difficult to achieve given the presence of significant dead tree material on the foreshore. As the slopes are the same as
existing, final profiling below low tide will likely be achieved by tidal velocities.

5.3 Methodology for Filling Containers

Filling sand-filled geotextile containers can be undertaken in a number of ways. The simplest methodology includes the

following
1, Dredge along the structure alignment to achieve the design depth
2. Roll out empty container
3. Secure in location with anchor blocks
4,  Fillcontainer using dredge (while excavating for the next container, per step 1)
5. Seal trunks

There are a number of potential variations to this generic methodology. These include:

Excavation for containers may source nourishment and container fill may be sourced from the dredging of channel.
Containers may be filled using a jet-pump suspended from a barge-mounted excavator.

Containers may be filled from an onshore stockpile using a hopper-fed jet pump.

Material may be double handled in some cases.

A frame may be used to secure the container instead of anchor blocks.

It is noted that the works will require the use of divers.

Works will be tide and weather dependent.

 

5.4 Methodology for Constructing Rock Wall
The general methodology for construction of the rock wall at the end on of the Noosa Spit is as follows:

Rock will be delivered to site by body trucks via Hasting Street and access track direct to Dog Beach.
Transported by suitable truck along nourished beach to the end of the Noosa River Spit.

Rocks will then be placed to achieve approximate profile using tipping barge.

The excavator will be used to ensure proper profile and interlocking of armour rock. Note: no need to clear access
track for construction; access via backfill along back of structure

 

 

 

Used in these records

About this file

File size
4.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Approved Concept Environment Management Plan OPW11_0116.01.pdf · 4.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.