Noosa Council documents
nt,
Town Planning Consent Permit - TPC 2714 Page 4
15. Roof and surface water is to be collected on site and discharged to a point
satisfactory to the Shire Engineer. A registered Hydraulics Consultant is to design
the stormwater disposal system and ensure that no scour or damage or
concentration of stormwater will occur to adjoining properties. A Building
Approval shall not be granted until the Shire Engineer and Building Surveyor has
approved of the drainage scheme.
16. Provision of approved refuse containers in accordance with the requirements of the
Refuse Management Regulations of 1983 for the storage and collection of refuse
to the satisfaction of Council’s Environmental Health Officer.
a 17, Provision of an imperviously paved area upon which to stand all refuse containers
together with a suitable enclosure, if required, to enclose the refuse container area
to the satisfaction of the Environmental Health Officer.
se,
18. Any flat or unit intended to be let out for fee or reward is to be licensed annually
with Council’s Health Department in accordance with the provisions of Chapter
43 of Council’s By-Laws prior to such letting.
19. Submission of a cash bond or trading bank guarantee to the sum of $4,000 to
secure performance of conditions, prior to the issue of Building Approval. The
cash bond or trading bank guarantee will be returned upon performance of the
conditions of approval. Council will retain this bond to particularly ensure
retention of existing trees on the site.
20. The provisions of this approval are to be effected, prior to the commencement of
the approved use. Council reserves the right to call upon the bond or guaranteed
sum referred to in this approval for the purposes of litigation should the use not be
( conducted in accordance with this approval.
21, The Town Planning Consent Permit may be revoked pursuant to Section 4.14 of
the Local Government (Planning and Environment) Act if commencement of
erection or works have not been made in accordance with that Permit or the rights
conferred by that Permit are not exercised within two (2) years of the date of issue
of the Permit.
22. The Town Planning Consent Permit lapses where:-
a. the use or erection of a building or other structure associated with the use,
has not been commenced within four (4) years of the date of issue of the
Town Planning Consent Permit, unless application is made and approved by
Council for an extension; or
b. the use of any premises pursuant to the Town Planning Consent Permit
ceases for a period of twelve (12) months.
Print Date: 21 January 2021, 3:51 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.