Council archive · source document
SPA Decision Notice - 010.2010.00000515.001 [As Published] · 152010.515
Officer: Jack Lewis
Direct Telephone: (07) 5449 5183
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: 2010/515
Your Reference: 94787
21 July 2010
CadCon Surveying & Town Planning
PO Box 5774
MAROOCHYDORE BC QLD 4558
Dear Sir / Madam
Decision Notice
Sustainable Planning Act 2009
I refer to your application and advise that on 21 July 2010 Council decided to approve the application
in full subject to conditions.
Details of the decision are as follows:
1 APPLICATION DETAILS
Application No: 2010/515
Street address: 2 & 4 Delorme Street, 28 & 30 Wyandra Street NOOSA HEADS
Real property description: Lots 126 & 127 RP160425, Lots 51 & 52 RP139776
Planning Scheme: The Noosa Plan
2 DECISION DETAILS
The following type of approval has been issued:
Development Permit for Reconfiguring a Lot - (4 lots into 2 lots)
3 RELEVANT PERIOD OF APPROVAL
The relevant period for this development approval is identified in the Assessment Manager
conditions.
4 ASSESSMENT MANAGER CONDITIONS
Planning Assessment
General
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development and as may be amended by these conditions. The approved
plan is listed in the following table.
Plan / Document No. Issue. Plan / Document Name Date
094787 Rev 4 Proposal Plan – CadCon Surveying & 20 May 2010
Town Planning
Page 1 of 8
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
2010/515
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
Existing Vegetation
3. The existing Melalueca species along the eastern boundary of the site shall be retained.
4. Vehicular pavements within the drip zone of the existing Melalueca species along the eastern
boundary shall be designed as a pervious pavement (such as grass paving cells or similar).
This will allow water that falls on this surface to penetrate to the trees root system. The
pavement shall be constructed so as not to damage the tree or their root system, in this regard
temporary fencing shall be provided around the trees during construction to help protect them.
Plans shall be submitted to the Council for approval that clearly show the type and extent of
the pervious pavement and the temporary fencing prior to obtaining a Development Permit for
Operational Works.
5. Trimming of overhanging branches of the Melalueca species trees along the eastern boundary
for access shall be carried out pursuant to an arborist report approved by Council.
6. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use.
7. All trees above 2m in height shall be retained, until an application for building works has been
approved for proposed lot 2.
Relevant Period
8. The relevant period is four (4) years from the day this permit takes effect and ends on
21 July 2014. During which time all conditions must have been complied with, operational
works completed, and the Plan of Survey lodged with the Council for endorsement.
Operational Works Assessment
Plan of Survey
9. In conjunction with the lodgement of the Plan of Survey for Council endorsement, legal
documentation must be presented to Council and submitted in the correct form with the fees
prescribed in Council's adopted fee schedule.
10. All outstanding rates and charges due and payable to Sunshine Coast Regional Council in
respect of the lots being reconfigured must be paid prior to endorsement of the Survey Plan.
11. Any changes required by Council’s Solicitor must be attended to prior to endorsing the Plan of
Survey. Any necessary Titles Office forms requiring the consent of Council is to be submitted
prior to the endorsing of the Plan of Survey.
12. Prior to Council endorsing the Plan of Survey, a certificate from a registered Professional Civil
Engineer shall be submitted to Council for each Development Permit for Operational Works
issued pursuant to this permit. The engineer shall certify those works and that they have been
completed in a workman like manner in accordance with good engineering practice and in
accordance with that permit.
Vehicle Access
13. A vehicle access to proposed Lot 1 shall be constructed from the eastern property boundary in
Wyandra Street. The access shall be a commercial standard and shall:
13.1 Be located between the two melalueca species trees on the eastern boundary generally
as shown on drawing number 094787-Rev 4 prepared by Cadcon dated 20 May 2010;
13.2 Extend from the property boundary to the edge of the formation of the existing
carparking area; and
Page 2 of 8
Page 3
2010/515
13.3 Be aligned and linemarked along the southern end of the carparking area to provide the
necessary width (6 metre maximum) and maintain the maximum number of parking
spaces.
In this regard plans detailing this work shall be prepared and submitted to Council for approval
prior to obtaining a Development Permit for Operational Works.
14. As part of the Building Works Approval, a Road/Footpath Permit in accordance with Council’s
Local Law No.8 shall be completed and submitted for the construction of the access driveway
to proposed Lot 2. The access shall:
14.1 Be located along the Delorme Street frontage. No vehicle access is permitted to
Wyandra Street;
14.2 Extend from the edge of the road formation in Delorme Street to the property boundary;
14.3 Be located clear of any existing services and footpaths; and
14.4 Be constructed in accordance with Council’s standard drawings, which will be provided
at time of approval.
15. All paths, driveways and parking areas shall be designed and constructed to ensure
pedestrian safety using non-slip materials, to produce an evenly graded surface finish, and to
be in accordance with the Disability Discrimination Act 1992 and Australian Standard 1428.1
Design for Access & Mobility.
16. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel,
footpath paving and landscaping such as trees and grasses in accordance with Council’s
Standard specifications prior to Council endorsing the Plan of Survey.
Power Supply
17. An electricity service shall be provided to each Lot unless already provided.
In this regard, an approved ENERGEX Electrical Design Consultant shall work in conjunction
with the Sunshine Coast Regional Council (SCRC) CEO delegate to prepare detailed designs
of the electrical proposal.
The detailed designs shall then be submitted to ENERGEX for approval and a copy of their
approval submitted to SCRC in conjunction with a “Certificate of Electricity Supply for
Proposed Subdivisions” (prepared by an approved ENERGEX Electrical Design Consultant)
prior to SCRC endorsing the Plan of Survey.
Any agreement with ENERGEX or an approved ENERGEX Electrical Design Consultant shall
be wholly at the applicant’s expense and shall not entail a financial encumbrance on future
purchasers of the proposed lots.
18. All redundant services, and any services that stand within another lot, shall be removed prior
to Council endorsing the Plan of Survey.
Telecommunications
19. The requirements for TELECOMMUNICATION services shall be satisfied in relation to the
provision of new telephone services to the proposed lots. In this regard written confirmation
from an approved telecommunication agency shall be submitted to the Council prior to Council
endorsing the Plan of Survey.
20. All redundant services, and any services that stand within another lot, shall be removed prior
to Council endorsing the Plan of Survey.
Roof Water & Stormwater Drainage
21. Stormwater runoff from proposed Lot 1 shall be connected to Council’s existing drainage
system in Wyandra Street.
22. Stormwater runoff from proposed Lot 2 shall be connected to Council’s existing drainage
systems in Wyandra Street and Delorme Street.
Page 3 of 8
Page 4
2010/515
23. Any filling or retaining works must not direct overland flows onto any adjoining properties.
Erosion and Sediment Control
24. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard, plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General Engineering Requirements
25. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be
submitted in conjunction with an application for a Development Permit for Operational Works.
In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
submitted in conjunction with any application for Operational Works.
26. Digital detailed designs including drawings, calculations, etc, shall be submitted with any
application for a Development Permit for Operational Works in respect of roadworks and
stormwater drainage works. The design shall be in accordance with Council’s Planning
Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and Earthworks.
To avoid conflict with underground pipes or services, all existing and proposed services
required by the development shall be shown on the plans.
27. To facilitate production of As Constructed drawings it is suggested that all design drawings are
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
28. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
29. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
30. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
UnityWater
Water & Sewerage
31. Reticulated water must be provided to each lot in the development. This must include:
31.1 Ensuring that existing internal water pipes are wholly contained within the lot they will
serve; and
31.2 An approved water meter for each lot in accordance with Sunshine Coast Water
Standard Drawings SCW 350,355 and 360.
32. Reticulated sewerage must be provided to each lot in the development and include existing
sewer house drains are wholly contained within the Lot they will serve.
Page 4 of 8
Page 5
2010/515
33. Any stormwater retention systems and gross pollutant traps must maintain a minimum
clearance of 1.5 metres from Council water supply and sewerage infrastructure.
34. Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from Council water
mains and 1.5 metres from Council sewerage mains. Landscaping plants within these
clearances must be low growing when mature and suitable Council approved varieties.
35. Water meters must be located on alternative boundaries to electrical pillars.
36. Construction works undertaken in the vicinity of Council water supply or sewerage
infrastructure must not adversely affect the integrity of the infrastructure. All costs associated
with repair, replacement or alteration of infrastructure must be met by the applicant.
5 REFERRAL AGENCY CONDITIONS
Not applicable.
6 APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
Plan / Document No. Issue. Plan / Document Name Date
094787 Rev 4 Proposal Plan – CadCon Surveying & Town 20 May 2010
Planning
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is advised that a Compliance Permit for all plumbing and drainage works within
the boundaries of the development site shall be obtained from Council’s Plumbing Services
Section prior to obtaining a Development Permit for Building Works.
2. Connection to the Council live water supply and live sewerage system must be undertaken by
Council at the applicants cost.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.
Page 5 of 8
Page 6
2010/515
8 PROPERTY NOTES
1. The applicant is advised that the following property note (or similar) will be created on
Council’s rates records for proposed Lot 2 to advise potential purchasers of Council’s
requirements regarding access:
“Private Certifiers, owners and prospective purchasers are notified that special access
requirements apply to this parcel of land. Contact Council’s Planning Department for details”.
9 PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable.
10 FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Operational Works Access, Stormwater and Erosion & Sediment Control
11 SELF ASSESSABLE CODES
Not applicable.
12 SUBMISSIONS
Not applicable.
13 REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable.
14 RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Sustainable Planning Act 2009 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a “negotiated decision notice” will be
issued. Only one “negotiated decision notice” may be given. Taking this step will defer your appeal
period, which will commence again from the start the day after you receive a “negotiated decision
notice”. (Refer to Part 8 “Dealing with decision notices and approvals” - Division 1 “Changing
decision notices and approvals during applicant’s appeal period” of the Sustainable Planning Act
2009.)
15 OTHER DETAILS
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,
Denis Wallace
Senior Development Planner
Enc: Appeal Rights
Approved Plans/Documents
Page 6 of 8
Page 7
2010/515
Appeal Rights
SUNSTAINABLE PLANNING ACT 2009 & SUSTAINABLE
PLANNING REGULATION 2009
The following is an extract from the Sustainable (ii) the length of a period mentioned in
Planning Act 2009 (Chapter 6). section 341 for the approval.
(3) However, a submitter may not appeal if the
MATERIAL CHANGE OF USE, RECONFIGURING A submitter—
LOT & OPERATIONAL WORKS
(a) withdraws the submission before the
Division 8 - Appeals to court relating to application is decided; or
development applications
(b) has given the assessment manager a
461 Appeals by applicants notice under section 339(1)(b)(ii).
(1) An applicant for a development application (4) The appeal must be started within 20
may appeal to the court against any of the business days (the submitter’s appeal
following- period) after the decision notice or
(a) the refusal, or the refusal in part, of a negotiated decision notice is given to the
development application; submitter.
(b) any condition of a development approval, 463 Additional and extended appeal rights for
another matter stated in a development submitters for particular development
approval and the identification or inclusion applications
of a code under section 242 (1) This section applies to a development
(c) the decision to give a preliminary application to which chapter 9, part 7
approval when a development permit was applies.
applied for; (2) A submitter of a properly made submission
(d) the length of a period mentioned in for the application may appeal to the court
section 341;; about a referral agency’s response made by
(e) a deemed refusal of the development a prescribed concurrence agency for the
application. application.
(3) However, the submitter may only appeal
(2) An appeal under subsection (1)(a), (b), (c) or
against a referral agency’s response to the
(d) must be started within 20 business days
extent it relates to—
(the applicant’s appeal period) after—
(a) if a decision notice or negotiated decision (a) if the prescribed concurrence agency is
notice is given—the day the decision the chief executive (environment)—
notice or negotiated decision notice is development for an aquacultural ERA; or
given to the applicant; or (b) if the prescribed concurrence agency is
(b) otherwise—the day a decision notice was the chief executive (fisheries)—
required to be given to the applicant. development that is—
(3) An appeal under subsection (1)(e) may be (i) a material change of use of
started at any time after the last day a premises for aquaculture; or
decision on the matter should have been (ii) operational work that is the removal,
made. damage or destruction of a marine
plant
462 Appeals by submitters - general
(4) Despite section 462(1), the submitter may
(1) A submitter for a development application
appeal against the following matters for the
may appeal to the court only against-
application even if the matters relate to code
(a) the part of the approval relating to the assessment—
assessment manager’s decision about
(a) a decision about a matter mentioned in
any part of the application requiring
section 462(2) if it is a decision of the
impact assessment under section 314; or
chief executive (fisheries);
(b) the part of the approval relating to the
(b) a referral agency’s response mentioned in
assessment manager’s decision under
subsection (2).
section 327.
464 Appeals by advice agency submitters
(2) To the extent an appeal may be made under
subsection (1), the appeal may be against 1 (1) Subsection (2) applies if an advice agency, in
or more of the following— its response for an application, told the
assessment manager to treat the response
(a) the giving of a development approval; as a properly made submission.
(b) any provision of the approval including— (2) The advice agency may, within the limits of its
(i) a condition of, or lack of condition jurisdiction, appeal to the court about—
for, the approval; or
Page 7 of 8
Page 8
2010/515
(a) any part of the approval relating to the 467 Appeals about changing or cancelling
assessment manager’s decision about conditions imposed by assessment
any part of the application requiring manager or concurrence agency
impact assessment under section 314; or (1) A person to whom a notice under section
(b) any part of the approval relating to the 378(9)(b) giving a decision to change or
assessment manager’s decision under cancel a condition of a development approval
section 327 has been given may appeal to the court
(3) The appeal must be started within 20 against the decision in the notice.
business days after the day the decision (2) The appeal must be started within 20
notice or negotiated decision notice is given business days after the day the notice of the
to the advice agency as a submitter. decision is given to the person.
(4) However, if the advice agency has given the For Building Works Only
assessment manager a notice under section 532 Appeals by applicants
339(1)(b)(ii), the advice agency may not
appeal the decision. (1) If—
465 Appeals about decisions relating to (a) a person has been given, or is entitled to
extensions for approvals be given—
(1) For a development approval given for a (i) an information notice under the
development application, a person to whom a Building Act about a decision
notice is given under section 389, other than other than a decision under
a notice for a decision under section 386(2), that Act made by the
may appeal to the court against the decision Queensland Building Services
in the notice. Authority; or
(2) The appeal must be started within 20 (ii) an information notice under the
business days after the day the notice of the Plumbing and Drainage Act
decision is given to the person. 2002 about a decision under
part 4 or 5 of that Act; or
(3) Also, a person who has made a request
under section 383 may appeal to the court (b) a person—
against a deemed refusal of the request (i) was an applicant for a building
(4) An appeal under subsection (3) may be development approval; and r
started at any time after the last day the (ii) is dissatisfied with a decision
decision on the matter should have been under the Building Act by a
made. building certifier or referral
agency about inspection of
466 Appeals about decisions relating to
building work the subject of the
permissible changes)
approval; the person may
(1) For a development approval given for a appeal against the decision to
development application, the following a building and development
persons may appeal to the court against a committee.
decision on a request to make a permissible
(2) An appeal under subsection (1) must be
change to the approval—
started within 20 business days after the day
(a) if the responsible entity for making the the person is given notice of the decision.
change is the assessment manager for (3) If—
the application—
(a) under the Building Act, a person makes
(i) the person who made the request; an application other than a building
or development application to a local
(ii) an entity that gave a notice under government; and
section 373 or a pre-request (b) the period required under that Act for the
response notice about the request
local government to decide the
(b) if the responsible entity for making the application (the decision period) has
change is a concurrence agency for the passed; and
application—the person who made the (c) the local government has not decided
request.. the application; the person may appeal
(2) The appeal must be started within 20 to a building and development
business days after the day the person is committee against the lack of the
given notice of the decision on the request decision and for the committee to decide
under section 376. the application as if it were the local
(3) Also, a person who has made a request government.
under section 369 may appeal to the court (4) An appeal under subsection (3) must be
against a deemed refusal of the request. started within 20 business days after the end
(4) An appeal under subsection (3) may be of the decision period..
started at any time after the last day the
decision on the matter should have been
made.
Page 8 of 8
Used in these records
SPA Decision Notice - 010.2010.00000515.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 61 KB (small file)
- File type
No other editions are linked here.