Decision Notice - Approved by Delegation of Authority - RAL26 0001 (As Published)
Officer: Matthew Pinese
Direct Telephone: 07 5329 6245
Our Reference: RAL26/0001
Your Reference: n/a
18 August 2026
CL Trompf & AP Trompf
C/- Brennan Planning Pty Ltd
44 Maple St
COOROY QLD 4563
[email protected]
Dear Marcus,
Decision Notice
Planning Act 2016
I refer to your application and advise that on 13 August 2026, Council decided to approve the
application, subject to conditions.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: RAL26/0001
Street address: 25 Tulip Street, Cooroy Qld 4563
Real property description: Lot 58 on RP32777
Planning Scheme: Noosa Plan 2020 (26 September 2025)
2. DECISION DETAILS
Council decided to issue the following type of approval:
• Development Permit for a Reconfiguring a Lot - Residential
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
When Conditions Must Be Complied With
1. Unless otherwise stated, all works required by the conditions of this Decision Notice must be
completed prior to submission of the subdivision plan to Council for compliance assessment.
ABN 97.969.214.121 PO Box 141
noosa.qld.gov.au Tewantin QLD 4565
[email protected] 07 5329 6500
Page 1 of 6
Document Set ID: 25061670
Version: 4, Version Date: 18/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 5 pages
Page 2
Currency Period
2. This development approval lapses if the requirements of the conditions have not been
completed and an application for plan seal is not lodged with Council by 13 August 2030
unless an application to extend the currency period is approved by Council.
Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
25-6646AA - Plan of Proposed Reconfiguration of Lot 58 on 21/10/2025
RP32777, prepared by Max Watterson & Associates
4. All lot numbering on the subdivision plan to be submitted to Council for compliance
assessment must remain as shown on the Approved Plans.
5. The easement documentation for the access easement over proposed Lot 1 must include
terms that permit the owner and occupier of Lot 1 to access and use the easement area for
the purpose of undertaking ongoing inspection, repair and maintenance of any building, roof
drainage infrastructure or associated services located on, or forming part of, Lot 1.
6. Certification must be submitted to Council from all relevant service providers (Energex, NBN)
which certifies that the development has met the requirements of this Decision Notice and
all applicable legislation at the time of construction.
7. Prior to Council signing the Plan of Survey, landscaping must be established along the full
eastern side of the access easement shown on the Approved Plans. The landscaping must
comprise Syzygium australe planted at 1.0 metre centres, with each plant being a minimum
1.0 metre in height and supplied in a minimum 200mm pot size at the time of planting. The
landscaping must be maintained in a healthy condition and any dead, damaged or diseased
plants must be replaced.
ENGINEERING
Property Access and Driveways
8. A residential driveway must be constructed to service Lots 1 and 2. The works must be
undertaken in accordance with an Operational Works approval and be generally in
accordance with Auxilium Consulting’s Operational Control Layout Plan (C902, Rev. B) dated
20 July 2026.
Stormwater Drainage
9. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with the Queensland Urban
Drainage Manual and be generally in accordance with Auxilium Consulting’s Stormwater
Management Report (Rev. 3) dated 21 July 2026.
10. Prior to Council signing the Plan of Survey, certification from a suitably qualified person
(RPEQ) must be provided to Council certifying that proposed Lots 1 and 2 have been
provided with a Lawful Point of Discharge pursuant to sections 3.6 and 3.9 of the Queensland
Urban Drainage Manual in a manner that does not substantially damaging a third-party
property.
Services
11. Reticulated electricity and telecommunication services must be provided to each lot in
accordance with the standards and requirements of the relevant service provider.
12. Unless otherwise stipulated by telecommunications legislation at the time of construction, the
development must be provided with all necessary conduits, pits and pipes to accommodate
the future connection of optic fibre technology telecommunications.
Page 2 of 6
Document Set ID: 25061670
Version: 4, Version Date: 18/08/2026
Page 3
13. Certification must be submitted to Council from all relevant service providers (Energex, NBN
and Unitywater) which certifies that the development has met the requirements of this
Decision Notice and all applicable legislation at the time of construction.
Easements
14. A 4.5-metre-wide easement for the purpose of access and services must be registered
against the titles of the properties in favour of proposed Lot 2 over the proposed easement
identified on the Approved Plans.
15. Unless otherwise agreed in writing by the relevant service provider, any public or third-party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
16. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
17. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
18. All earthworks and associated batters/retaining structures, both above and below ground
level, both temporary and permanent, must be contained entirely within the subject site
unless written permission from the respective landowner(s) is provided to Council. All
earthworks must be undertaken in accordance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
19. Where the development involves excavation or filling over, or adjacent to, drainage, water
supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
provide a freeboard of 100mm above the finished ground surface level.
Damage to Services and Assets
20. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
- 3 Stormwater Management Report, prepared by Auxilium 21 July 2026
Consulting
- - Engineering File Note, prepared by Auxilium Consulting 10/11/2025
6. REFERRAL AGENCIES
Not applicable.
Page 3 of 6
Document Set ID: 25061670
Version: 4, Version Date: 18/08/2026
Page 4
7. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part
of the assessment manager conditions:
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qld.gov.au/Planning-and-
Development/Development-tools-and-guidelines/Infrastructure-Charges
Building and Construction Industry (Portable Long Service Leave) Levy
2. The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.
Co-ordination of Operational Works Assessment
3. Additional application fees apply to Operational Work applications where the different
aspects of the works are lodged separately. Significant savings in application fees will result
if all works are lodged in a single application.
Preparation of a Preliminary Construction Management Plan
4. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD).
b. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.
c. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Private Infrastructure
5. All private infrastructure for the development must be designed to meet the planning scheme
requirements unless otherwise agreed by the relevant authority.
Road Reserve Permit
6. This development permit provides the applicant with written authority to undertake the
development in accordance with the conditions. Any additional activities that are undertaken
inside Council’s road reserve for the purpose of acting on this development permit may
require a Road Reserve Permit. These additional activities may include, but are not limited
to, hoarding, pedestrian diversions, laneway closures, etc. To apply for a Road Reserve
Permit, or for more information, Contact Council’s Road Reserve Officer at
[email protected] Sealing
7. All works required by this permit must be completed and accepted by Council prior to
submitting an application for plan sealing.
Page 4 of 6
Document Set ID: 25061670
Version: 4, Version Date: 18/08/2026
Page 5
Biosecurity Act 2014 – Fire Ant Control
8. Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
individuals and businesses are responsible for ensuring that they follow the movement
controls for specific organic materials to help prevent the spread of fire ants within South
East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
ant biosecurity zone may need a biosecurity instrument permit. More information is available
on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
8. PROPERTY NOTES
Not applicable.
9. VARIATION APPROVAL DETAILS
Not applicable.
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Operational Works Road work, Stormwater and Drainage work
Development Permit for Building Works All building work.
11. SUBMISSIONS
Not applicable.
12. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
13. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully
Matthew Pinese
Development Planner | Development Assessment
Development & Regulation
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
Page 5 of 6
Document Set ID: 25061670
Version: 4, Version Date: 18/08/2026
Page 6
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 6 of 6