Original source · versioned page text
Project Management Plan
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Processes for delivery of concrete (including exclusion zones, spotters, movement of agitators, traffic control, etc.);
Arrangements for erection, dismantling and climbing (satellite booms only); and
Any other issues that may impact on the safe operation of the placement boom such as the proximity of:
Overhead power lines; and
Cranes, structures and other plant.
3.13.5 Training and competence
Subcontractors using major plant at the work site must also ensure that operator/s and associated crews:
Are appropriately licensed, if required by law;
Have undertaken refresher and familiarisation training if required;
Are sufficiently experienced or competent to perform the work required at the work site; and
If using earthmoving equipment, can provide evidence of an old earthmoving licence specific to the class of equipment they
will be operating or equivalent evidence of competence if operator does not hold a licence.
3.14 Electrical supply and use of electrical equipment
All electrical switchboards and equipment supplied by the Principal Contractor will be maintained by a nominated electrical
contractor.
3.14.1 Power source
Power source will be
Existing older building with no RCD protection of the power circuits - subcontractors must provide portable RCD’s connected
upstream from any electrical equipment in use.
New work - the Principal Contractor will provide RCD-protected electrical supply at convenient locations throughout the work
site, including every level on a multi-level building and on the top level of a slip or jump form (where applicable).
No network supply available - Diesel generator will be provided by the Principal Contractor.
Work in remote areas of the work site where no power source is available - the subcontractor will supply a portable generator
with sufficient load capacity to undertake the work.
Work areas within the building require the maximum allowable electrical lead length to be exceeded - Multiple boards will be
provided on the same levels by the Principal Contractor.
3-phase supply not available at a temporary board - The subcontractor will supply an appropriate generator if using 3-phase
equipment.
Temporary power boards will also be provided by the Principal Contractor in the locations listed below (provide details below)
Temporary power board locations are (details)
One on each level
3.14.2 Electrical equipment
All subcontractors must ensure that all electrical equipment in their control or to be used by their workers on site complies with
AS/NZS 3012 Electrical Installations – Construction and Demolition Sites.
Subcontractors will be required to ensure:
All extension leads are of the heavy duty type and do not exceed:
25 metres (1mm conductor diameter);
35 metres (1.5mm conductor diameter);and/ or
60 metres (2.5mm conductor diameter).
No double adaptors, piggy-back plugs or domestic grade power boards are used on site;
All leads, power tools and other electrical equipment are properly maintained;
All electrical equipment is tested and tagged by a competent person within legal timeframes (see table below); and
Updated and current test and tag registers for any electrical equipment used on site are provided to the Principal Contract
WHSMP-C 01/2018.8 Initials Page 23 of 39
____ ____
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.