Project Management Plan

Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                Processes for delivery of concrete (including exclusion zones, spotters, movement of agitators, traffic control, etc.);
                Arrangements for erection, dismantling and climbing (satellite booms only); and
                Any other issues that may impact on the safe operation of the placement boom such as the proximity of:
                       Overhead power lines; and
                       Cranes, structures and other plant.



3.13.5 Training and competence
Subcontractors using major plant at the work site must also ensure that operator/s and associated crews:
        Are appropriately licensed, if required by law;
        Have undertaken refresher and familiarisation training if required;
        Are sufficiently experienced or competent to perform the work required at the work site; and
        If using earthmoving equipment, can provide evidence of an old earthmoving licence specific to the class of equipment they
        will be operating or equivalent evidence of competence if operator does not hold a licence.


3.14 Electrical supply and use of electrical equipment
All electrical switchboards and equipment supplied by the Principal Contractor will be maintained by a nominated electrical
contractor.
3.14.1 Power source
Power source will be
   Existing older building with no RCD protection of the power circuits - subcontractors must provide portable RCD’s connected
upstream from any electrical equipment in use.
   New work - the Principal Contractor will provide RCD-protected electrical supply at convenient locations throughout the work
site, including every level on a multi-level building and on the top level of a slip or jump form (where applicable).
   No network supply available - Diesel generator will be provided by the Principal Contractor.
   Work in remote areas of the work site where no power source is available - the subcontractor will supply a portable generator
with sufficient load capacity to undertake the work.
   Work areas within the building require the maximum allowable electrical lead length to be exceeded - Multiple boards will be
provided on the same levels by the Principal Contractor.
   3-phase supply not available at a temporary board - The subcontractor will supply an appropriate generator if using 3-phase
equipment.
   Temporary power boards will also be provided by the Principal Contractor in the locations listed below (provide details below)
Temporary power board locations are (details)
One on each level


3.14.2 Electrical equipment
All subcontractors must ensure that all electrical equipment in their control or to be used by their workers on site complies with
AS/NZS 3012 Electrical Installations – Construction and Demolition Sites.
Subcontractors will be required to ensure:
        All extension leads are of the heavy duty type and do not exceed:
                25 metres (1mm conductor diameter);
                35 metres (1.5mm conductor diameter);and/ or
                60 metres (2.5mm conductor diameter).
        No double adaptors, piggy-back plugs or domestic grade power boards are used on site;
        All leads, power tools and other electrical equipment are properly maintained;
        All electrical equipment is tested and tagged by a competent person within legal timeframes (see table below); and
        Updated and current test and tag registers for any electrical equipment used on site are provided to the Principal Contract




WHSMP-C 01/2018.8                                               Initials                                                 Page 23 of 39

                                                 ____                          ____
Log in to download the original file

Project Management Plan.pdf · 350 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.