Project Management Plan

Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Subcontractors will also be required to
   Supply task lighting should the need arise
   Provide portable RCDs if power supply has no other RCD protection
   Provide a sufficient number of non-conductive leads stands or hangers for use by their workers
   Other requirements (provided details below)
Other requirements (details)

Inspection & testing frequency for electrical equipment
All portable electrical equipment must be visually checked by the user, prior to each use. Any damaged equipment must be either
discarded or tagged and put out of service until repaired.
Item                                                                              Frequency
Extension leads                                                                   3 months
Power tools                                                                       3 months
Portable socket outlet assemblies                                                 3 months
Portable lights                                                                   3 months
Other electrical equipment with flexible lead connection                           3 months
Portable RCD                                                                      Before every use (push button)
                                                                                  3 months (electrician test)
Permanent RCD                                                                     Monthly (push button)
                                                                                  12 months (electrician test)
Powered site sheds                                                                6 months
Temporary switchboards                                                            6 months
Temporary wiring (construction wiring)                                            6 months


3.15 Essential services
Where necessary and if practicable, the Principal Contractor will arrange to have services which are likely to be hazardous if
disturbed, isolated before work starts.
3.15.1 Underground services
Underground services                       Have been identified at the work site by the Principal Contractor as listed below
                                           Have NOT been identified at the work site
The following underground services have been identified by the Principal Contractor at the work site
   Electrical
   Gas
   Water supply
   Stormwater
   Sewerage
   Fuel lines and tanks
   Telecommunications cables
   Other (provide details below)
Other methods (details)

       Where excavation work is being undertaken, relevant information regarding the services will be provided to the
       subcontractor or made available in the site map section of this plan. Information provided will include the type, location and
       depth of the services as well as any necessary supplementary detail.
       The subcontractor must not commence excavation work without obtaining underground services information from the
       Principal Contractor beforehand.
Service locations will be identified using the following methods and/or sources




WHSMP-C 01/2018.8                                              Initials                                                 Page 24 of 39

                                                 ____                         ____
Log in to download the original file

Project Management Plan.pdf · 350 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.